Laserfiche WebLink
Journey Ventures, LLCFReclamatJ&T Consulting, Inc. <br />Journey Ventures Pit <br />9/8/2015 <br />Bond Quantities and Costs tpyfjcy <br />Consattlna Inc. <br />Phase 1 (3.66 acres) <br />lReclamation Operation Quantity Unit Unit Cost Cost <br />Scarifying Disturbed Area Phase 1 3.66 ac 200 732 <br />Topsoil Placement Disturbed Area Phase 1 3.66 ac 1,800 6,588 <br />Revegetate Disturbed Area Phase 1 3.66 ac 1,000 3,660 <br />Mobilization 1.0 Is 2,500 2,500 <br />cyd 1.50 <br />Total Direct Cost 13,480 <br />Overhead and Profit Cost (12.60%) $ 1,698 <br />Contract Cost $ 15,178 <br />Protect Management (9.25%) $ 1,404 <br />Total Required Financial Warranty For Phase 1 $ 16,582 <br />Phase 11A (2.15 acres) <br />lReclamation Operation Quantity Unit Unit Cost ost <br />Scarifying Disturbed Area Phase 11A 2.15 ac $ 200 $ 430 <br />Topsoil Placement Disturbed Area Phase 11A 2.15 ac $ 1,800 $ 3,870 <br />Revegetate Disturbed Area Phase 11A 2.15 ac $ 1,000 $ 2,150 <br />162,500 <br />Backfill Required to Fill Phase 7 to 2 ft Above Groundwater <br />Total Direct Cost $ 6,450 <br />Overhead and Profit Cost (12.60%) $ 813 <br />Contract Cost $ 7,263 <br />Project Management (9.25%) $ 672 <br />Additional Financial Warranty Required For Phase 11A $ 7,934 <br />Cummuladve Financial Warranty Required For Phase 1 6 11A $ 24,517 <br />Phase 2 (7.35 acres) <br />lReclamation Operation uantity Unit Unit Cost Cost= <br />Scarifying Disturbed Area Phase 2 7.37 ac $ 200 $ 1,474 <br />Topsoil Placement Disturbed Area Phase 2 7.37 ac $ 1,800 $ 13,266 <br />Revegetate Disturbed Area Phase 2 7.37 ac $ 1,000 $ 7,370 <br />162,500 <br />Backfill Required to Fill Phase 7 to 2 ft Above Groundwater <br />Total Direct Cost $ 22,110 <br />Overhead and Profit Cost (12.60%) $ 2,786 <br />Contract Cost $ 24,896 <br />Protect Management (9.25%) $ 2,303 <br />Additional Financial Warranty Required For Phase 2 $ Y7199 <br />Cummuladve Financial Warranty Required For Phase 1, 11A, 2 $ 51,716 <br />Phase 7 (6.53 acres) <br />Reclamation Operation Quantity Unit Unit Cost Cost <br />Backfill Required to Fill Phase 7 to 2 ft Above Groundwater (Haul <br />from Phases 1, 11A) 65,000 cyd 2.50 162,500 <br />Backfill Required to Fill Phase 7 to 2 ft Above Groundwater <br />OB from Phase 2) 40,000 cyd 1.50 60,000 <br />Scarifying Disturbed Area Phase 7 6.53 ac 200 1,306 <br />Topsoil Placement Disturbed Area Phase 7 6.53 ac 1,800 11,754 <br />Revegetate Disturbed Area Phase 7 6.53 ac 1,000 6,530 <br />Total Direct Cost 242,090 <br />Overhead and Profit Cost (12.60% <br />os) $ <br />30,503 <br />Contract Ct $ 272,593 <br />Project Management (9.25%) $ 25,215 <br />Additional Financial Warranty Required For Phase 7 $ 297,808 <br />Cummuladve Financial Warranty Required For Phases 1, 2, 11A, 7 $ 349,524 <br />2of6