Laserfiche WebLink
October 19, 2015 C-1982-056/Foidel Creek Mine JLE <br />Figure 4. 5MN Pipeline to be installed south of 6MN Reservoir. <br />The 16LT Utility Borehole was observed. The topsoil piles are vegetated and stable. The pad embankment near <br />the access road entrance is steep and cattle and wildlife have damaged the erosion control matting that was <br />installed on the slope. However, rills and gullies were not observed. TC was considering reclaiming this area, <br />however according to Mr. Nettleton, TC may need to use the pad in the future. Given this, TC should seed the <br />embankment area that is devoid of vegetation and monitor for possible erosion. <br />The WMD Stabilization BH site was observed. The area is vegetated and stable and the topsoil stockpiles is <br />vegetated and stable. <br />The 18LT Borehole is inactive. The topsoil stockpile is vegetated, stable and marked. No problems were <br />observed <br />The 15LT BoreholeNentilation Shaft pad was observed, the topsoil stockpile is vegetated and stable. No <br />problems were observed. <br />The explosives storage area/equipment storage area was observed. No problems were noted. <br />The BOB pile was observed and no problems were noted. The diversion ditch around the perimeter of the pile <br />was maintained and functional. <br />Figure 5. BOB Pile <br />TOPSOIL — Rule 4.06 <br />Removal 4.06.2; Substitute Materials 4.06.4(4); Storage and Protection 4.06.3; Redistribution 4.06.4: <br />The clay storage area above the CRDA was observed. This area is vegetated and stable. The topsoil <br />stockpile adjacent to the clay pile is vegetated and stable. <br />Number of Partial Inspection this Fiscal Year: 2 <br />Number of Complete Inspections this Fiscal Year: 2 <br />Page 8 of 12 <br />