Laserfiche WebLink
CRIPPLE CREEK & VICTOR GOLD MINING Co. <br />ANGLOGOLD ASHANTI (COLORADO) amec <br />SQUAW GULCH (VLF) WEEKLY REPORT foster <br />wheeler <br />CQA ACTIVITIES: <br />1) Field Activities: <br />The following activities were observed: Placement and compaction of the Phase 1 Structural Fill <br />materials; subgrade acceptance; placement, compaction, density testing, depth verification and <br />acceptance of Soil Liner Fill materials; geomembrane installation and acceptance; Drain Cover Fill <br />placement; leak detection construction; and pump monitoring at the LVSCS riser pipes. <br />11) Laboratory Activities: <br />Concrete testing (ADR2), atterberg limits, moisture, compaction, permeability and sieve analysis testing <br />continued. <br />The following samples were collected <br />General Project Items <br />Meetings and Discussions: <br />Phase 1 — <br />Soil Liner Fill; 1-SLF-39-R <br />Phase 1 — <br />Soil Liner Fill; 1-SLF-40-R <br />Phase 1 — <br />Soil Liner Fill; 1-SLF-41-R <br />Phase 1 — <br />Soil Liner Fill; 1-SLF42-R <br />Cameron <br />— Soil Liner Fill; SLF-193-C <br />The Weekly Contractor Meeting was held September 1, 2015 (Amec Foster Wheeler, CC&V, Ames). <br />Amec Foster Wheeler and CC&V discussed the barren pipeline corridor immediately following the Weekly <br />Contractor Meeting. <br />Ames daily safety meetings <br />Amec Foster Wheeler daily safety meetings <br />Summary of Concerns: None. <br />CC&V: Daily updates, reporting, and scheduling occurred between CC&V Projects, Amec Foster <br />Wheeler, and Ames. <br />Deliveries: None. <br />CQA Monitor/� <br />Submitted by: Date: September 9, 2015 <br />Bobby Redd, EI <br />Project Resident <br />Reviewed by: <br />CC&V Projects <br />Reviewed By: <br />Date: <br />Date: 9///��5 <br />Reviewed By: Date: <br />