CRIPPLE CREEK & VICTOR GOLD MINING Co. <br />ANGLOGOLD ASHANTI (COLORADO) amec <br />SQUAW GULCH (VLF) WEEKLY REPORT foster <br />wheeler <br />Subgrade: <br />Phase 1 areas dozed to finished grade were compacted per project plans and specifications. <br />See attached figure for approved subgrade. <br />Soil Liner Fill: <br />Cat dozers placed SLF between stations DO+00 to D6+00. A Cat dozer, a Cat smooth drum <br />roller, a Cat excavator and a water truck conditioned and compacted SLF between stations <br />DO+00 to D6+00. <br />Cat 740 haul trucks transported SLF to station DDO+00. A Cat dozer placed SLF upslope from <br />stations DDO+00 fo DD1+00. <br />Cat dozers placed SLF upslope from stations DDO+00 to DM2+00. A Cat dozer, a Cat smooth <br />drum roller, a Cat excavator and a water truck conditioned and compacted SLF upslope from <br />stations DDO+00 to DMO+00. <br />Cat 740 haul trucks transported SLF to stations G1+00 through G8+00. A Cat dozer placed SLF <br />in the vicinity of stations GO+00 to G9+00. <br />Cat 777 haul trucks transported SLF from the Cameron stockpile to station F4+00. A Cat dozer <br />stockpiled the SLF below the ADR haul road. <br />All of the above Soil Liner Fill material was placed, graded, and compacted per the project plans <br />and specifications. Moisture content, density testing and depth verification were performed per <br />project specification prior to surface acceptance and geomembrane installation. <br />See attached figure for approved SLF. <br />Drain Cover Fill: <br />Cat 740 haul trucks transported DCF from the stockpile to Phase 1. Low ground pressure Cat <br />dozers placed DCF on approved geomembrane in Phase 1. <br />See attached figure for approved DCF. <br />Underdrain System: <br />Primary Underdrain: Complete. <br />Secondary Underdrain: None. <br />Tertiary Underdrain: None. <br />Leak Detection: <br />None. <br />Miscellaneous: <br />Amec personnel continued LVSCS pump monitoring and observation. <br />