Laserfiche WebLink
CRIPPLE CREEK & VICTOR GOLD MINING Co. j <br />ANGLOGOLD ASHANTI (COLORADO) amec <br />SQUAW GULCH (VLF) WEEKLY REPORT foster <br />wheeler <br />Owner: Cripple Creek & Victor Gold Mining Co. Project Number: 74201125NO <br />Project: Squaw Gulch Valley Leach Fill (VLF) Week Ending: July 25, 2015 <br />Location: Cripple Creek & Victor Gold Mine, CO <br />Contractor: Ames Construction, Inc. <br />Reporting Period: 7.19.2015 through 7.25.2015 <br />Ambient Temperature Ranges During Week Weather Conditions During Week: <br />Highs: 59°F to 78°F Cloud Cover: Cloudy to Mostly Cloudy <br />Lows: 45°F to 51°F Precipitation: Rain <br />Wind: Calm to moderate <br />Ames: Continuing construction tasks for the Valley Leach Facility (VLF). <br />Planning: Continuing construction activities and scheduling for the VLF. <br />CONSTRUCTION ACTIVITIES AND PROGRESS: <br />1) Earthworks <br />A) VLF (PSSA, Phase 1, and 2) <br />Structural Fill: <br />The following Structural Fill haul to fill and grading activities occurred: <br />A Cat excavator loaded Cat 740 haul trucks with Structural Fill in the vicinity of station D10+00. A <br />Cat dozer placed the material between stations F24+00 to F28+00 and graded downslope <br />towards the D Bench. A Cat smooth drum roller compacted the fill area. <br />ADR Haul Road berm removed between stations 18+00 to 24+00. Material stockpiled for future <br />use as Structural Fill below Area 34 topsoil stockpile. <br />A Cat excavator loaded stockpiled material into Cat 740 haul trucks from the slope above the <br />ADR Haul Road station 19+00. The material was stockpiled below the Area 34 topsoil stockpile <br />for future use as Structural Fill in Phase 1 diversion channel closure. <br />A Cat dozer finish graded slopes between stations D10+00 to DM1+00 and FM4+00 to FM8+00. <br />A Cat smooth drum roller compacted subgrade between stations FM4+00 to FM11+00. <br />CC&V hauled material to the Dump 4 surge in Phase 2 using Cat 793 haul trucks. A Cat dozer <br />placed the Structural Fill between stations N20+00 and N22+00. A Cat smooth drum roller <br />compacted the fill area. <br />Days <br />S <br />M <br />T <br />I W <br />I T <br />F <br />S <br />Work Shifts <br />D <br />D <br />D <br />D <br />D <br />D <br />D <br />D=Day Shift N=Night Shift W= Weather <br />Ambient Temperature Ranges During Week Weather Conditions During Week: <br />Highs: 59°F to 78°F Cloud Cover: Cloudy to Mostly Cloudy <br />Lows: 45°F to 51°F Precipitation: Rain <br />Wind: Calm to moderate <br />Ames: Continuing construction tasks for the Valley Leach Facility (VLF). <br />Planning: Continuing construction activities and scheduling for the VLF. <br />CONSTRUCTION ACTIVITIES AND PROGRESS: <br />1) Earthworks <br />A) VLF (PSSA, Phase 1, and 2) <br />Structural Fill: <br />The following Structural Fill haul to fill and grading activities occurred: <br />A Cat excavator loaded Cat 740 haul trucks with Structural Fill in the vicinity of station D10+00. A <br />Cat dozer placed the material between stations F24+00 to F28+00 and graded downslope <br />towards the D Bench. A Cat smooth drum roller compacted the fill area. <br />ADR Haul Road berm removed between stations 18+00 to 24+00. Material stockpiled for future <br />use as Structural Fill below Area 34 topsoil stockpile. <br />A Cat excavator loaded stockpiled material into Cat 740 haul trucks from the slope above the <br />ADR Haul Road station 19+00. The material was stockpiled below the Area 34 topsoil stockpile <br />for future use as Structural Fill in Phase 1 diversion channel closure. <br />A Cat dozer finish graded slopes between stations D10+00 to DM1+00 and FM4+00 to FM8+00. <br />A Cat smooth drum roller compacted subgrade between stations FM4+00 to FM11+00. <br />CC&V hauled material to the Dump 4 surge in Phase 2 using Cat 793 haul trucks. A Cat dozer <br />placed the Structural Fill between stations N20+00 and N22+00. A Cat smooth drum roller <br />compacted the fill area. <br />