April 21, 2015 C- 1996 - 083 /Bowie No. 2 Mine JDM <br />Gob Pile #2 <br />Gob Pile #2 was wet due to recent precipitation events. A large portion of the wind -rowed materials on bench #5 <br />were spread and graded at the time of the inspection. A portion of bench 44 was also spread and graded. Small <br />pools of water were observed on the pile in the vicinity of the idle equipment. <br />GOB Pile Bench 94 <br />GOB Pile Bench #5 <br />During the inspection equipment was in the process regrading a roadside ditch to alleviate the water and allow it to <br />drain from the access road. <br />Lateral ditches D -F10, D -F11, and D -F6 were in good condition with problems noted. <br />Gob Pile #3 <br />Material was being compacted on the west side of the gob pile at the time of the inspection. The material noted on <br />the west side of the pile during the March 2015 inspection has been graded and spread with compaction activities <br />on -going during the inspection. <br />The under drain was discharging at the time of the inspection with a trickle discharge. <br />No problems were noted, with the exception of the following: <br />- Refuse material on the east side of the pile contained pooled water throughout. The Division understands that <br />this is a common occurrence after recent precipitation events; however, this area should be graded in such a <br />manner that no pooled water is on the pile. <br />Gob Pile 44 <br />Reclamation of the west side of Gob Pile #4 is completed. Cover material is placed on the three lower benches <br />that have been backfilled and graded to final configuration. The upper bench remains open for additional refuse <br />placement. Topsoil has been placed and erosion control mat is in place. A small amount of vegetative growth was <br />observed on the pile at the time of the inspection. <br />ROADS — Rule 4.03 Construction 4.03.1(3)14.03.2(3) Drainage 4.03.1(4)14.03.2(4) Surfacing and Maintenance <br />4.03.1(5) and (6)14.03.2(5) and (6) Reclamation 4.03.1(7)14.03.2(7): <br />All roads in and around the facilities area and off -site locations were wet and muddy, but stable with no problems <br />noted. <br />Number of Partial Inspection this Fiscal Year: 13 <br />Number of Complete Inspections this Fiscal Year: 3 <br />Page 5 of 7 <br />