April 21, 2015 C- 1996 - 083 /Bowie No. 2 Mine JDM <br />Items noted during the March 2015 inspection that have been addressed include: <br />- Culvert C -1323 was damaged at the inlet of the apron. This culvert has been addressed and no problems were <br />noted. <br />- Culvert C44 was approximately 1/4 full of sediment from the outlet to approximately halfway into the culvert. <br />This culvert has been cleared with no problems noted. <br />- Ditch D -J3 contained heavy sediment and has lost some design. This ditch has been cleared; however <br />approximately 4" of sediment remains in the areas of the ditch with minimal positive flow. Due to the minimal <br />slope of the ditch, sediment will tend to drop out during the course of flow. The ditch remains stable with no signs <br />of damage. Continual maintenance will be required to ensure that the sediment build -up does not jeopardize the <br />integrity of the ditch. <br />- The outlet of ditch D -C4 on the north side of the Portal Bench was blocked from coal material before the ditch <br />could enter culvert C -C4. This area has been addressed with no additional issues noted. <br />�.zeft' AW -1 '40L <br />Ditch D -C4 Cleanout to Culvert C -C4 <br />On -going maintenance items include: <br />- The northwest corner of the Terror Creek shaft pad rock -lined down -drain has been breached on the west <br />side of the drain. This area has slight down -cut and light erosion. This area should be addressed to ensure <br />that all run -off through the rock -lined drain is contained within the drain. <br />As noted in the March 2015 coal complete inspection, ditch D -1337 is designed to flow south along the conveyor <br />line between culverts C -1326 and C -1313. Culvert C -1313 then conveys the D -1337 flow to B- Gulch. Due to down - <br />cutting of D -1337 the operator cut a new ditch to carry flow from D -1337 to B -Gulch on the west side of the <br />conveyor, rather than realigning D -1337 to C-1313. BRL must maintain D -1337 as designed and remove the ditch <br />carrying flow under the conveyor line, or submit revised designs consistent with the current on -the- ground <br />configuration. <br />PROCESSING WASTE /COAL MINE WASTE PILES — Rule 4.10 and 4.11 Drainage Control; Surface <br />Stabilization; Placement: <br />Gob Pile #I <br />Gob Pile 91 has been inactive. Technical Revision No. 97 is currently under review to provide a variance from the <br />requirement of Rule 4.10.4(4) for 0.2 acres of Gob Pile #1 where the slope was identified as being greater than 2:1 <br />Number of Partial Inspection this Fiscal Year: 13 <br />Number of Complete Inspections this Fiscal Year: 3 <br />Page 4 of 7 <br />