CRIPPLE CREEK & VICTOR GOLD MINING Co. <br />ANGLOGOLD ASHANTI (COLORADO) amec <br />SQUAW GULCH (VLF) WEEKLY REPORT foster <br />wheeler <br />Spent Ore: <br />Mine Operations hauled and stockpiled spent ore (SO) periodicaly in the PSSA using Cat 793 <br />haul trucks and a Cat dozer. Spent ore elevations were maintained above the drain cover fill <br />grade by at least 20 feet for 793 haul traffic. <br />Spent ore was placed and compacted as engineered fill beneath the footprint of the ADR2 <br />foundation. CQA monitoring was observed by New Fields. <br />Ames placed SO around the high volume solution collection system (HVSCS) riser piping. Amec <br />confirmed that rubber tired and dozer equipment stayed clear of the riser pipes during placement. <br />The last of the HVSCS 24" vertical steel risers was extended in a 31.5' section. The HVSCS <br />piping was welded into place and included level indicator piping. Adjustments were made by <br />Ames surveyors to ensure proper installation and that they were vertically plumb. The pipes were <br />wrapped with geomembrane before burial per project plans and site instruction. <br />Snow was removed from the access road and the security area, hauled, and dumped on the <br />north side of the ADR2 platform outside of the footprint. <br />Subgrade: Phase 2 rough subgrade preparation occurred. No additional subgrade was <br />approved during this reporting period. <br />Cameron Site: SLF processing continued at the Cameron Site. <br />Underdrain System: <br />Primary Underdrain: Complete. <br />Secondary Underdrain: No work was performed during this reporting period. <br />Tertiary Underdrain: No work was performed during this reporting period. <br />Leak Detection: No work was performed during this reporting period. <br />B) Underground Workings: <br />None. <br />II) Storm Water Management <br />Best Management Practices (BMPs) are being performed. <br />