1.0 INTRODUCTION <br />This report summarizes construction observations and quality control testing performed <br />during the construction of the Wattenberg Resource, Pond 3 slurry wall. The slurry wall <br />was constructed by Envirocon Inc. ( Envirocon). Upon completion of mining, Pond 3 will <br />be reclaimed as a lined water storage reservoir meeting seepage requirements of the State <br />Engineer. The slurry wall was designed to meet these seepage requirements. <br />A total of approximately 10,045 lineal feet was constructed. The total curtain area of the <br />slurry wall was approximately 328,800 square feet. The construction consisted of trench <br />excavation with bentonite slurry to maintain the trench walls. The trench extended through <br />the site alluvial soils into the underlying bedrock. The trench was backfilled with low <br />permeability material derived from on -site fine grained materials mixed with dry bentonite <br />and excavated material and slurry. Upon completion of mining, the slurry wall will provide <br />the low permeability liner for a below grade water storage reservoir. <br />1.1 Site Description <br />The Wattenberg Mine is operated by Aggregate Industries (Al) and is located on an <br />alluvial terrace immediately west of the South Platte River approximately % mile northeast <br />of Weld County Road 23 % and approximately 1 mile north of Baseline Road (aka Weld <br />County Road 2), in Weld County, Colorado. <br />Pre - mining topography of the site slopes gently to the northeast. The north part of the <br />mine was previously mined. A stockpile is located southwest of the mined area. The <br />Huett Seep is located immediately east of the Pond 3 slurry wall. The Huett Seep is lined <br />with a geosynthetic clay liner (GCL) and replaces jurisdictional wetlands that previously <br />were present in the mine limits of Pond 3. Overhead Public Service Company of Colorado <br />power lines cross the slurry wall alignment at two locations. Two other power lines are <br />located north of the slurry wall. The screening and wash plant is located on the east side of <br />the river. <br />Z.0 CONSTRUCTIONSUMMARY <br />Prior to construction of the slurry wall, Dirt Doctors constructed a platform of fine grained <br />material along the inside of the slurry wall alignment. The platform consisted of select, <br />fine grained, overburden soils placed in sufficient quantity to provide supplemental fines to <br />the trenched material. Envirocon placed bentonite bags along the platform at calculated <br />distances to result in backfill with at least one percent bentonite based on the dry weight of <br />the backfill. <br />The typical Envirocon slurry wall construction crew consisted of five to six personnel <br />managed by one superintendent. Envirocon delivered two trailers to the site. One was set <br />up at the mine entrance and the other was set up on the north part of the site, south of the <br />previously mined area. This second trailer served as the site QA/QC trailer. <br />- 1 - August 2013 <br />P:\23514\ 133 - 23514 -13003 \Docs\Reports\ Wattenberg_Construction _Report_2013.doc <br />