"M -me <br />C) Geomembrane: <br />Phase 1 80 -mil DSMS LLDPE Liner Installation: (80 -mil liner installation is suspended at this <br />time.) <br />D) Drain Cover Fill (DCF) <br />Drain cover fill placement over approved liner was completed in the PSSA during the week of <br />November 15, 2014. Additional drain cover fill was placed at the vertical riser pipe area <br />completing the 4 -foot backfill over the 6" HVSCS PCPE piping. <br />Drain cover fill was pushed up to the top of the SGVLF haul road ramp in the PSSA against the <br />temporary loading ramp buttressing the structural fill of the SGVLF haul road ramp. <br />The drain cover fill surface on the ADR pad was graded. <br />E) High Volume Solution Collection System Piping ( HVSCS): <br />No work was performed during this reporting period. <br />II) Storm Water Management <br />Best Management Practices (BMPs) are being performed. <br />CQA ACTIVITIES: <br />1) Field Activities: Field activities and observation during this reporting period included: Slope grading <br />and fill placement; DCF grading in the PSSA; DCF, SF, and SLF sampling; clearing and grubbing; <br />underground working remediation. <br />II) Laboratory Activities: Permeability, Atterberg limits, moisture, and sieve analysis laboratory testing <br />continued. <br />The following samples were collected and returned to AMEC's laboratory for analysis: <br />➢ Drain cover fill samples DCF -117C and DCF -118C (Control samples) <br />➢ Soil Liner Fill sample SLF -165C (Control sample from the Cameron site) <br />Y Structural Fill samples SF -105R to SF -111 R (Record samples from Phase 1 and Phase 2) <br />2014- 11- 22 -MLE2 WEEKLY FINAL Page 3 of 7 <br />