Laserfiche WebLink
Ah <br />CRIPPLE CREEK & VICTOR GOLD MINING Co. <br />ANGLOGOLD ASHANTI (COLORADO) <br />SQUAW GULCH (VLF) WEEKLY REPORT <br />Owner: Cripple Creek & Victor Gold Mining Co. Project Number: 74201125NO <br />Project: Squaw Gulch Valley Leach Fill (VLF) Week Ending: November 22, 2014 <br />Location: Cripple Creek & Victor Gold Mine, CO <br />Contractor: Ames Construction, Inc. <br />Reporting Period: 11.16.2014 through 11.22.2014 <br />Ambient Temperature Ranges During Week Weather Conditions During Week: <br />Highs: 24 °F to 44 °F Cloud Cover: Partly cloudy <br />Lows: 4 °F to 26 °F Precipitation: None. <br />Wind: Variable <br />Ames: Continuing construction tasks for the Valley Leach Facility (VLF). <br />Planning: Continuing construction activities and scheduling for the VLF. <br />CONSTRUCTION ACTIVITIES AND PROGRESS: <br />1) Earthworks <br />A) VLF (PSSA, Phase 1, and 2) <br />Topsoil /Overburden Stripping: None. <br />Tree Grubbing and Clearing, Chipping: Tree removal occurred in the Phase 2 area between <br />the rip rap stockpile and the Phase 2 Diversion Channel. <br />Production Drilling: None. <br />Production Blasting: None. <br />Structural Fill: <br />An AMEC field professional monitored fill material temperature placed within the fill areas. <br />Average structural fill temperatures were above 32 °F. All structural fill material discussed below <br />was placed in a maximum nominal thickness of 3 feet and compacted per the project technical <br />specifications. <br />2014- 11- 22 -MLE2 WEEKLY FINAL Page 1 of 7 <br />Days <br />S <br />M <br />T <br />W <br />T <br />F <br />I S <br />Work Shifts <br />D <br />D <br />D <br />D <br />D <br />N <br />N <br />N <br />N <br />D =Day Shift N =Night Shift H= Holiday <br />Ambient Temperature Ranges During Week Weather Conditions During Week: <br />Highs: 24 °F to 44 °F Cloud Cover: Partly cloudy <br />Lows: 4 °F to 26 °F Precipitation: None. <br />Wind: Variable <br />Ames: Continuing construction tasks for the Valley Leach Facility (VLF). <br />Planning: Continuing construction activities and scheduling for the VLF. <br />CONSTRUCTION ACTIVITIES AND PROGRESS: <br />1) Earthworks <br />A) VLF (PSSA, Phase 1, and 2) <br />Topsoil /Overburden Stripping: None. <br />Tree Grubbing and Clearing, Chipping: Tree removal occurred in the Phase 2 area between <br />the rip rap stockpile and the Phase 2 Diversion Channel. <br />Production Drilling: None. <br />Production Blasting: None. <br />Structural Fill: <br />An AMEC field professional monitored fill material temperature placed within the fill areas. <br />Average structural fill temperatures were above 32 °F. All structural fill material discussed below <br />was placed in a maximum nominal thickness of 3 feet and compacted per the project technical <br />specifications. <br />2014- 11- 22 -MLE2 WEEKLY FINAL Page 1 of 7 <br />