Laserfiche WebLink
amee, <br /> Subgrade: <br /> All subgrade areas in the PSSA footprint have been certified for soil liner fill (SLF) placement per <br /> project technical specifications. <br /> Two dozers were slope grading subgrade downslope of the south perimeter road stations P4+00 <br /> to P8+00 in the Phase 1 area. <br /> Soil Liner Fill: <br /> The following soil liner fill (SLF) areas in the PSSA were compacted per project technical <br /> specifications to finished grade, inspected, and certified for geomembrane placement: <br /> Between approximate stations A18+00 to A22+00 and the PSSA floor adjoining <br /> previously approved SLF. This completes SLF surfaces approvals within the PSSA <br /> footprint. <br /> See the attached SLF acceptance map for all accepted locations. <br /> Excess SLF was cut and regraded in the northeast corner of the PSSA below station A21+00. <br /> The excess SLF was hauled to the stockpile above station DD5+00. <br /> Cat 777 haul trucks transported soil liner fill from the stockpile near Dump 4 and from the <br /> Cameron processing location to an area below stations FO+00 to F10+00 where it was stockpiled <br /> for future use for Phase 1. <br /> Low Volume Solution Collection Fill: <br /> The following Low Volume Solution Collection Fill (LVSCF) areas in the PSSA were placed to <br /> finished grade per project specifications, inspected, and certified for primary geomembrane <br /> placement: <br /> r The western half of the PSSA southern embankment. <br /> See the attached LVSCF map for all placement and accepted locations for primary geomembrane <br /> deployment. <br /> SLF Processing: <br /> Cameron Site: No SLF mining or processing occurred at the Cameron Site. However, Ames <br /> began transporting the Cameron stockpiled SLF to a new stockpile located below stations FO+00 <br /> to F10+00 in the Phase 1 area. The processing equipment remains at the Cameron site. No new <br /> processing was performed during this reporting period. <br /> Underdrain System: <br /> Primary Underdrain: Complete. <br /> Secondary Underdrain: No work was performed during this reporting period. <br /> Tertiary Underdrain: Complete within the PSSA footprint. <br /> B) Underground Workings <br /> Underground workings UG#6639, UG#6640, and UG#6461 were blasted in conjunction wiih <br /> production cut blasting. Additional remediation is required. <br /> Confirmatory drilling occurred at underground workings UG #6461 and UG#6639. Additional <br /> remediation is required. <br /> 2014 08 30-MLE2 WEEKLY FINAL Page 2of8 <br />