ti <br />Aft <br />➢ Riprap processing resumed <br />➢ Slope grading occurred adjacent to Highway 67 between the MSE wall and the PSSA <br />➢ Boulders were placed at the ends on both sides of the timbered facade MSE wall for protection. <br />➢ Surface drainage channels above both ends of the MSE were graded, lined with geotextile, and <br />then lined with riprap <br />➢ The ditch adjacent to Highway 67 between the MSE wall and the PSSA was realigned, lined with <br />geotextile, and then lined with riprap <br />Deliveries: 36 rolls of 80 -mil LLDPE geomembrane DSMS liner was delivered to ECA. <br />Submitted by: Eric Lorenson Date: August 27, 2014 <br />Reviewed by: Date: August 27, 2014 <br />Andrea Medun <br />Project Engineer <br />Phone: 719 - 689 -2986 <br />CC &V Projects <br />Approved By: Date: g /5 /� q <br />Approved By: Date: <br />2014.08.23 -MLE2 WEEKLY FINAL Page 5 of 8 <br />