Weekly construction quality assurance report week ending 8/23/14
From
CC&V
To
DRMS
Email Name
TC1
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
13
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
amec <br />Material cut upslope from stations A16 +00 to A21 +00 was loaded into Cat 740 haul trucks and <br />transported to ADR haul road stations 20 +00 to 25 +00. Some of the material was also hauled <br />upslope of stations D0 +00 to D2 +00. The material was placed as structural fill. <br />An excavator removed material from upslope of station D10 +00 and loaded it into Cat 740 trucks. <br />The material was hauled to stations F24 +00 to F26 +00 where it was placed as structural fill. <br />Furthermore, two dozers pushed material downslope to the fill area at stations F24 +00 to F26 +00 <br />from stations H18 +00 to H2O +00. <br />The Phase 2 Diversion Channel was compacted with a smooth drum roller and prepared for <br />geofabdc and riprap placement east of the Phase 2 pond. <br />Subgrade: <br />All subgrade areas in the PSSA footprint have been certified for SLF placement per project <br />technical specifications. <br />The subgrade was inspected and certified below stations F0 +00 to F10 +00 in the Phase 1 area. <br />Soil Liner Fill: <br />The following SLF areas in the PSSA were compacted per project specifications to finished <br />grade, inspected, and certified for geomembrane placement: <br />r Between approximate ADR haul road stations 3 +00 to 7 +00 and the central portion of the <br />PSSA floor adjoining previously approved SLF (reapproved). <br />r Between approximate ADR haul road stations 7 +00 to 10 +00 and the northern portion of <br />the PSSA floor adjoining previously approved SLF. <br />Soil liner fill was reconditioned on the PSSA floor and the northern PSSA slopes. <br />A Cat smooth drum roller compacted the SLF surface from Bench A to the PSSA floor between <br />stations A20 +00 to A22 +00. <br />Ames cut through a small area of secondary liner to expose and cap the temporary embankment <br />drain on the south side of the PSSA. After the underdrain was capped, SLF was placed and <br />compacted in the drain repair area and the liner was repaired. All work performed was observed <br />by AMEC QA personnel and was completed in accordance with project technical specifications. <br />See the attached SLF acceptance map for all accepted locations. <br />Low Volume Solution Collection Fill: <br />The following Low Volume Solution Collection Fill ( LVSCF) areas in the PSSA were placed to <br />finished grade per project specifications, inspected, and certified for primary geomembrane <br />placement: <br />Y No low volume fill was certified for geomembrane placement during this reporting period. <br />See the attached LVSCF map for all placement and accepted locations for primary geomembrane <br />deployment. <br />SLF Processing: <br />2014.08.23 -MLE2 WEEKLY FINAL Page 2 of 8 <br />