SECTION O1 30 00 <br />ADMINISTRATIVE REQUIREMENTS <br />PART 1 GENERAL <br />1.1 SECTION INCLUDES <br />A. Coordination and project conditions. <br />B. Field engineering. <br />C. Preconstruction meeting. <br />D. Progress meetings. <br />1.2 COORDINATION AND PROJECT CONDITIONS <br />A. Coordinate scheduling, submittals, and Work of various sections to ensure efficient and <br />orderly sequence of installation of interdependent construction elements. <br />B. Coordinate completion and clean-up of Work of separate sections in preparation for <br />Substantial Completion. <br />1.3 FIELD ENGINEERING <br />A. Employ Land Surveyor registered in State of Colorado and acceptable to Owner. <br />B. Locate and protect survey control and reference points. Promptly notify Engineer of <br />discrepancies discovered. <br />C. Control datum for survey is that shown on Drawings. <br />D. Verify set -backs and easements; confirm drawing dimensions and elevations. <br />E. Provide field engineering services. Establish elevations, lines, and levels, utilizing <br />recognized engineering survey practices. <br />F. Submit copy of liner drawings signed by Land Surveyor depicting elevations and <br />locations of the as constructed Work. <br />G. Maintain complete and accurate log of survey control work as Work progresses. <br />H. Protect survey control points prior to starting site work; preserve permanent reference <br />points during construction. <br />I. Promptly report to Engineer loss or destruction of reference point or relocation required <br />because of changes in grades or other reasons. <br />NCCI Pit #1 Reservoir Liner - Technical Specifications Administrative Requirements <br />013000- 1 <br />