amec-- <br /> A Cat dozer graded the subgrade in the Phase 2 Diversion Channel alignment area east of the <br /> Phase 2 pond. <br /> A Cat 345 excavator was shaping the slope from stations H10+00 to H12+00. <br /> Cat dozers placed cut to fill between stations 1-14+00 to H8+00 downslope to stations F8+00 to <br /> F12+00. <br /> A Cat 320 excavator was building berms along Bench DID from DD6+00 to DD8+00. <br /> A Cat 330 excavator with a rock hammer broke oversized rock on the subgrade near station <br /> A22+00. <br /> A Cat loader moved material from Bench B to the inboard Phase 1embankment above the 9,450' <br /> elevation bench on the south side of the PSSA and placed it as structural fill. <br /> Cat dozers were finish grading and a Cat smooth drum roller compacted subgrade in various <br /> areas within PSSA and surrounding Phase 1 slopes. <br /> Soil liner fill (SLF)was transported from the Squaw Gulch SLF stockpile to the stockpile area <br /> above station DD5+00 in Phase 1 Area 1. SLF was also hauled and placed in areas of the PSSA <br /> below stations A16+00 to A20+00. <br /> A dozer spread SLF downslope of station A16+00 to A20+00. The material was placed in <br /> approximately 18-inch lifts and brought to the area in Cat 740 haul trucks that were loaded from <br /> the SLF stockpile on the PSSA floor. <br /> Subgrade: <br /> The following subgrade areas in the PSSA were compacted per project technical specifications to <br /> finished grade, inspected, and certified for SLF placement: <br /> From approximate stations A18+00 to A20+00 to the PSSA floor <br /> := From approximate ADR road stations 6+00 to 7+00 to the PSSA floor <br /> See the attached subgrade acceptance map for all accepted subgrade locations. <br /> Soil Liner Fill: <br /> The following SLF areas in the PSSA were compacted per project specifications to finished <br /> grade, inspected, and certified for geomembrane placement: <br /> From approximate stations B12+00 to B14+00 to the ADR haul road. <br /> See the attached SLF acceptance map for all accepted locations. <br /> SLF Processing: <br /> Cameron Site: No SLF mining or processing occurred at the Cameron Site. Approximately <br /> 244,860 tons of SLF material has been produced and remains stockpiled at the Cameron Site for <br /> future use. The SLF processing equipment remains at the Cameron site. No new processing <br /> was performed during this reporting period. <br /> Underdrain System: <br /> Primary Underdrain: Complete. <br /> Secondary Underdrain: Select structural fill was placed over the remaining portion of the <br /> secondary underdrain that was started the previous week located between station A21+00 and <br /> 2014.08.02-MLE2 WEEKLY FINAL Page 2 of 3 <br />