Idaho Mine <br /> Bond Estimate <br /> May Day 4daho Mine Complex <br /> M-1981-195 <br /> The Access Road will remain after mining-including access to Incas Mine Site located east of the Chief Portal(See Attachment A) <br /> Ore will not be processed within the May Day-Idaho Mine Complex <br /> Buildings will be removed at cost of material(material recycled costs exceed of cost to remove or demolish) <br /> Mine equipment will be buried underground(approved by the Land Owner-Mr.David Tippit) <br /> Access road to the Idaho Mill will remain to support post mine land uses <br /> Existing Bond 4/9/2007 Comments <br /> Dewatering Tailing Pond $ 1,364.00 <br /> Demolish Buildings $ 1,354,00 <br /> Grade Tailings Pond $ 1,129.OD <br /> Grade Augmentation Pond $ 452.00 <br /> Seal lower Idaho Mill Adit $ 2,164.00 <br /> Remove Waste Rods Stockpile $ 195.00 <br /> Grade Topsoil $ 2,864.00 8 acres @$2,864 <br /> Rip Compacted Area $ 802.00 <br /> Revegetation $ 13,825.00 8 acres @$1,382.50 acre 2765 <br /> Mobilize/Demobilize $ 1,071.00 <br /> Total $25,220.00 <br /> Proposed Bond <br /> Dewatering Tailing Pond Deleted from Mine Plan <br /> Demolish Buildings Deleted from Mine Plan <br /> Grade Tailings Pond Deleted from Mine Plan <br /> Grade Augmentation Pond Deleted from Mine Man <br /> Seal Lower Idaho Mill Adit $ 2,164.00 <br /> Remove Waste Rock Stockpile $ 195.00 To be removed under remedial 2014-15 activities <br /> Grade Topsoil $ 2,864.00 2 acres <br /> Rip Compacted Area $ 802.00 <br /> Revegetation $ 2,765.00 2 acres @$1,382.50 <br /> Mobilize/Demobilize $ 1,071.00 <br /> Total $ 9,116LOD <br /> Liability Insurance 2.02% $ 199.19 <br /> Performance Bond LOS% $ 103.54 <br /> Job Superintendent $ 25.00 39.38 Hr. $ 98450 <br /> Profit(10%) 10% $ 986.10 <br /> %of existir Hours total hr. <br /> 0.390999 64 25.02395 <br /> Finacial Work Prep $ 500.00 <br /> Eng Work/Contract Bid 4.25%% $ 419.09 <br /> Reclamation Management 5%% $ U61L00 <br /> Total $14,314.43 <br />