Notes for site visit June 18, 2014: <br />arrived on site and met with Gary Harding. We focused on the <br />maintenance items discovered with Susan Burgmaier during last <br />week's inspection. Areas of observation are; <br />Loadout /Gob Pile #3 Area <br />-Move the waddle above C -K2. Complete. <br />-There is a waddle shown on the map north of the coal loading <br />building that needs to be installed. Complete. <br />•Regrade ditches J 15 & J 16 — Not vet complete <br />-Clean inlet of culvert J5 - Complete <br />-Replace silt fence along fire mountain canal at conveyor <br />crossing where sedimentation has pulled it down - Complete <br />-Put bales /waddles at headwalls of bridge over Fire Mountain <br />Canal. Possibly grade the high spot in the road south of the <br />bridge - Complete <br />Haul Road up to Mine office area: <br />-Repair the waddle before C -B19 - Complete. <br />-The silt fence by the bath house needs maintenance — Not vet <br />complete <br />-C lean inlets of culverts B -7, C12, C7, C15, C19, C3- Did not <br />inspect, will inspect next site visit <br />-Curve 6 ditch (C14) need regraded and riprap replaced - <br />Complete <br />-Clean out ditch B -8 below material storage area, at Culvert C8 <br />— Not vet complete <br />-Berm at Curve 9 material storage area expansion is necessary <br />and will be built and should remain on the map - Complete <br />-The disturbed area markers east of D -Bench need to be placed <br />upright — Not yet complete and will change based on MR -153 <br />submittal <br />Gob Pile #2 Area <br />-At gob pile #2 there is an area below D -F12 that is too steep <br />and needs to be graded back — Scheduled to be completed June <br />19. <br />-Repair the straw bales around topsoil stockpiles D & E - <br />Complete <br />-Remove the remnants of silt fence near pond F - Complete <br />-Remove or replace silt fence south of Pond F along old rail bed <br />- Complete <br />