Laserfiche WebLink
Bulldozer Worksheet Cont'd Task#001 Page 2 of 2 <br /> Dozing method: 1.100 (50%SL) <br /> Visibility: 1.000 (AVG.) <br /> Job efficiency: 0.830 (1 SHIFT/DAY) <br /> Spoil pile: 1.000 (DOZ-OC) <br /> Push gradient: 1.115 (CAT HB) <br /> Altitude: 1.000 (CAT HB) <br /> Material Weight: 0.868 (CAT HB) <br /> Blade type: 1.000 (PAT) <br /> Net correction: 0.7290 <br /> Adjusted unit production: 906.29 LCY/hr <br /> Adjusted fleet production: 906.29 LCY/hr <br /> JOB TIME AND COST <br /> Fleet size: 1 Dozer(s) _ <br /> Unit cost: $0.280/LCY <br /> Total job time: 57.24 Hours <br /> Total job cost: $14,523.44 <br /> C[RCES Cost Estimating Software <br />