ameO <br />2.0 SUMMARY OF EARTHWORK CONSTRUCTION <br />Earthworks activities associated with the 2011 Phase 5 VLF OSA 2nd Portion included the <br />following: <br />• Site grading, including cut/fill and blasting of non - rippable bedrock; <br />• Leak Detection System (LDS) construction, including trench excavation, <br />installation of pipe, placement of LDF, and geosynthetics installation; <br />• Subgrade preparation; <br />• SLF installation, placement and compaction, depth verification testing, <br />and preparation of SLF surface for geomembrane deployment; <br />• OSA primary liner system installation; <br />• DCF placement above the primary geomembrane layer; and <br />• Placement of HVSCS piping. <br />Ames generally used the following equipment during construction: <br />• Caterpillar D6 Low Ground Pressure (LGP) Dozer; <br />• Caterpillar D7 LGP Dozer; <br />• Caterpillar D8 LGP Dozer; <br />• Caterpillar D9 LGP Dozer; <br />• Caterpillar D9 Dozer; <br />• Caterpillar D10 Dozer; <br />• Caterpillar 279 Skidsteer; <br />• Bobcat Skidsteer; <br />• Caterpillar 950 Loader; <br />• John Deere 544 Loader; <br />• Caterpillar 966 Loader; <br />AMEC Earth & Environmental, Inc <br />2000 S Colorado Blvd 2 -1000 <br />Denver, CO 80222 <br />Tel 303 - 935 -6505 <br />Fax 303 - 935 -6575 www amec.com <br />7 <br />