IV)VLF Geosynthetics <br />A) Geomembrane Installation <br />1) VLF <br />Geomembrane installation within the Phase 5 VLF continued performing deployment, <br />seaming, and repair /QC activities. Geomembrane installation was performed in the area shown <br />on Figure 3. Approximately 149,989 square feet of primary 100mil LLDPE was deployed <br />using a John Deere 200 excavator and a John Deere 544 front -end loader with spreader -bar <br />attachments. Subgrade was inspected and approved by AMEC and Lone Star representatives <br />prior to geomembrane deployment (see Figure 3). Approximately 8,433 linear feet of seam was <br />fusion welded using to two fusion welding machines. Nineteen destructive test samples were <br />marked during fusion seaming. All destructive tests performed were within project <br />specifications. Non - destructive testing was performed for fusion welded seams. Repairs were <br />performed using the extrusion welding method for all marked defects. Vacuum testing was <br />performed for all extrusion welded seams and repairs. <br />Geomembrane installation and acceptance is complete for the Phase 5 PSSA. <br />B) Anchor Trench <br />1) VLF <br />Anchor trench excavation was performed between stations J0 +00 ( + / -) and J3 +00 ( + / -) and <br />between stations A48 +00 ( + / -) and A53 +00 ( + / -) using a CAT 312 excavator and laborers. An <br />AMEC representative observed and inspected the anchor trench excavation. The trench was <br />found to be constructed in accordance with design drawings and project specifications. <br />Anchor trench backfill was performed between stations C4 +00 ( + / -) and C4 +50 ( + / -) using a <br />John Deere 35D excavator, a jumping jack compactor, and laborers. An AMEC representative <br />observed and inspected the anchor trench backfill. The trench was found to be backfilled in <br />accordance with design drawings and project specifications. <br />C) Geomembrane Acceptance <br />1) VLF <br />Primary 100mil geomembrane (P -290 thru P -313, P -416 thru P -495, P -523, P -537 thru P -577, <br />and P -580 thru P -696) shown on Figures 4a and 4b were inspected by AMEC and Lonestar <br />representatives and found to be installed within project specifications and acceptable for <br />continued construction activities. <br />D) Geomembrane Delivery <br />1) VLF <br />Three loads of LLDPE geomembrane rolls were delivered to site during the week. The loads <br />were delivered on flat bed trucks in good condition (7 rolls of 80mil single sided textured and <br />28 rolls of 100mil smooth). The rolls were unloaded using a CAT 950 front -end loader with <br />forks attached. The geomembrane was placed on three pieces of HDPE pipe, stacked two rolls <br />high. An AMEC field representative inventoried the geomembrane and was present at all times <br />during unloading of the geomembrane. <br />VLF Weekly Report WE 10.16.10.1) <br />