AM <br />GENERAL PROJECT ITEMS <br />Summary of Concerns: <br />No concerns <br />Summary of Planning Items: <br />Continue SLF placement within the Phase 5 VLF footprint. <br />Continue geomembrane installation within the Phase 5 VLF footprint. <br />Continue anchor trench backfill. <br />Continue installation of the high volume solution collection system. <br />Continue DCF placement. <br />Continue ore placement at south toe berm. <br />Summary of Non - conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC &V: <br />CC &V held a Weekly Construction meeting on September 28, 2010. Items discussed included Safety, <br />Environmental, Schedule, QC documentation, and CQA. <br />AMEC. <br />None <br />Others: <br />None <br />Summary of Incidents /Accidents/Health & Safety Issues: <br />None <br />We trust the information provided clearly represents our findings and observations for the week ending <br />October 2, 2010. <br />Joseph D. Hickey, CQA Monitor Date: October 2, 2010 <br />Approved By: Date: 10 /11 /10 <br />VLF Weekly Report WE 10.02.10.1) <br />