Laserfiche WebLink
ameO <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC &V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co. <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ VLF <br />Date: February 13, 2010 <br />Reporting Period: 2/7/10 through 2/13/10 <br />Days <br />S <br />M <br />T <br />W <br />T <br />F <br />S <br />Work Shifts <br />- <br />D <br />D <br />D <br />D <br />D <br />- <br />- <br />N <br />N <br />N <br />N <br />N- <br />D = Day Shift N = Night Shift <br />Project No.: 84201125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day/Night <br />Ambient Temperature Range (F): Low: 10 °F to 17 °F ( + / -) High: 26 °F to 34 °F <br />AMEC CQA: Personnel On -site through the Reporting Period (See Attachment A). <br />AMES: No issues <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />II) EARTHWORKS <br />A) Clearing and Grubbing <br />1) VLF <br />Clearing and grubbing was finished at the East Cresson Clay Borrow using a CAT 330 <br />excavator, a CAT D -6 dozer and, two 40 -ton haul trucks. Trees /slash was stockpiled in a <br />designated area within the clay borrow area. <br />B) Stripping <br />1) VLF <br />Topsoil stripping was performed during the haulage of clay material to the plant using one <br />CAT D -6 dozer and one CAT D -8 dozer at the East Cresson Clay Borrow. Haulage of topsoil <br />to the East Cresson Clay Borrow topsoil stockpile continued. <br />Future topsoil stripping will be performed as the borrow excavation progresses. <br />C) Subgrade Preparation <br />1) VLF <br />No work performed during the week. <br />VLF Weekly Report WE 02.13.10.D.doc <br />