ameldo <br />Summary of Planning Items: <br />Structural fill placement within the Phase 5 VLF footprint will continue. <br />Continue processing soil liner fill at the South Cresson Clay Processing area. <br />Continue subgrade preparation within the Phase 5 VLF footprint. <br />Continue construction of the ADR and Crusher waterlines. <br />Confirmation drilling for Underground Workings #3006, #3007, and #3009. <br />Summary of Non - conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC &V.• <br />CC &V held a Weekly Construction meeting on December 8, 2009. Items discussed included Safety, <br />Environmental, Schedule, QC documentation, and CQA. <br />Ames Construction: <br />Daily Safety /Tailgate Meetings: AMEC personnel attended the Ames daily safety meeting held prior to <br />the start of shift. Discussions centered on safety and planned work activities. <br />AMEC. <br />None <br />Others: <br />None <br />Summary of Incidents /Accidents/Health & Safety Issues: <br />None <br />We trust the information provided clearly represents our findings and observations for the week ending <br />December 12, 2009. <br />Joseph D. Hickey, CQA Monitor Date: December 12, 2009 <br />Approved By: �_ Date: 12/15/2009 <br />VLF Weekly Report WE 12.12.09.D.doc <br />