Laserfiche WebLink
Cripple Creek & Victor Gold Mining Company <br />Mill Site Earthworks Project <br />Final Report <br />Quality Assurance Monitoring & Test Results <br />January 31, 2014 <br />R1 4ft <br />W?Vr416 <br />• For open workings the excavations were backfilled with CSB to approximately <br />10 feet below the finished surface grade. The surface of the CSB was compacted <br />using the shovel from a CAT excavator. A minimum 3- foot -thick concrete plug was <br />cast into the shaft and allowed to cure for a minimum of 7 days. A minimum 7 -foot- <br />thick layer of cemented rockfill was then placed onto the concrete plug. SF was <br />then placed to the final grade, as needed. In some cases, the excavation did not <br />require placement of CSB prior to placement of the concrete plug and cemented <br />rockfill. <br />• For collapsed workings, collapsed materials were excavated to a depth of 25 feet <br />below finished grade. The excavations were either backfilled with CSB to <br />approximately 3 feet below the soil /bedrock interface or shaped for placement of a <br />concrete plug. The surface of the CSB was compacted using the shovel from a <br />CAT excavator. A minimum 3- foot -thick concrete plug was cast into the shaft and <br />allowed to cure for 7 days. A minimum 7- foot -thick layer of cemented rockfill was <br />then placed over the concrete plug. After the cemented rockfill was allowed to <br />cure, SF was then placed to the final grade, as needed. <br />• Shallow surface pits that were less than 25 feet deep below the final SLF subgrade <br />surface were excavated to bedrock or pit termination. The pits were then backfilled <br />with compacted SSF and SF to the final subgrade elevation. <br />• In some cases, shallow surface pits were completely removed during slope re- <br />contouring and required no further remediation. <br />2.1.2 Remediation of Lateral /Inclines /Adits <br />A number of laterals and adits were identified within the Mill Site Earthworks footprint. <br />Per the remediation recommendations, underground workings were identified within 50 <br />feet of the existing grade elevation were remediated. Workings that were deeper than <br />50 feet below the final grade elevation were not remediated. <br />Remediation for laterals and adits consisted of drilling nominal 3- inch - diameter blast <br />holes into the crown pillar (the rock between the ground surface and the roof of the <br />working) using a pneumatic hammer track drill rig. The blast holes were loaded and <br />the crown pillars blasted into the mined void. For some of the shallower workings, the <br />blasted material was excavated and replaced with compacted fill. For deeper blasted <br />laterals that could not be fully and safely excavated, three layers of geogrid separated <br />by a layer of Select Structural Fill was placed 15 feet beyond the mine working limits. <br />All blast holes that did not intercept the underground working or were not incorporated <br />in the blast were completely grouted with bentonite slurry prior to blasting the crown <br />pillar and remediating the working. <br />Underground working remediation activities for the Mill Site Earthworks Project were <br />performed from December 2011 through July 2012. <br />8 <br />