Topic: Sediment Control <br />As an addition to the Reclamation Plan, we enclose Exhibit F -3 which is an Erosion and <br />Fugitive Dust Control Plan for all stockpiles. When the action described in Exhibit F -3 is <br />completed in 2014, the operator will submit evidence of the work to DRMS. <br />The operator commits to removing and/or relocating the Phase 2 stockpile beginning in <br />the January- February 2014 timeframe. The operator agrees to complete the <br />removal /relocation by May 30, 2014. The operator will notify the DRMS that it has <br />begun the removal /relocation on or before February 28, 2014 and provide photographic <br />documentation by June 7, 2014 that the process is complete. <br />Thank you for your assistance in analyzing the data to determine the corrective actions. <br />Cordially, <br />Tuttle & Associates <br />U • Jv <br />Gary J. T ttle <br />Encl <br />Cc: Andre, Mark, Bud <br />1) <br />