Laserfiche WebLink
Table E -2 Reclamation Timetable <br />Year <br />Comments <br />Length of time to <br />complete (Years) <br />1 <br />Site preparation; access road construction, truck scale <br />installation, etc. <br />0.25 <br />Mining of deposit with concurrent reclamation. <br />1 -27 <br />26.23 <br />Backfill and topsoil final highwall and seed. Cease <br />dewatering <br />27 <br />0.08 <br />Remove truck scale, rip road and all topsoiled areas, and <br />reseed all disturbed areas. <br />27 <br />0.08 <br />Total <br />26.65 <br />5. Revezetation Plan <br />The areas being reclaimed will be harrowed and drill seeded in the spring and fall with a mix <br />consisting of the following in order to control erosion: <br />Tomichi Pit, December 2013 E -3 <br />