Mr. Michael Cunningham <br />CDRMS <br />November 26, 2013 <br />6.3.3 Exhibit C - Mining Plan <br />5. The Division is currently reviewing Technical Revision No. 4 (TR -04) which addresses <br />changes to the TSF liner and leak detection system. Please revise all applicable portions <br />of Exhibit C that change as the result of the approval of TR -04. <br />Response: The following changes will be made to Exhibit C: <br />Section 4.3.2 Subgrade Preparation. Insert new bullet No 11. <br />"Install Geocomposite Drainage Layer (GDL) between embankment and <br />Geocomposite Clay Liner (GCL) to protect GCL during installation." <br />(new) Section 4.3.4 Geocomposite Drainage Layer <br />"A US Fabrics, Inc 220GN Geocomposite Drainage Layer, or equivalent, will be <br />placed on the interior slopes and bottom where there are seeps to protect the <br />GCL from premature hydration during the installation process. The GDL will be <br />installed concurrently with the GCL, leak detection system, and polypropylene <br />geomembrane liner. GDL specifications and installation instructions are <br />presented in Appendix 4 -1.4, Geocomposite Drainage Layer." (See Attachment <br />8) <br />Appendix 4 -1.4 will be added to Exhibit C. <br />• Section 4.3.5 Leak Detection System. Change last sentence in third <br />paragraph. <br />"If ground water is detected (indicating a leak in the GCL), the level will be <br />monitored, a small pump will be installed in the PVC pipe, the ground water will <br />be pumped to the impoundment, and the Division will be notified within 48 hours <br />from first detection." <br />Section 4.3.8 QA /QC, Onsite Personnel. Change to read: <br />"UMC's mill manager or qualified designee will be on site at all times <br />construction activates are being conducted by UMC crews or by contractor <br />crews. UMC has retained an Owner's Engineer, who is a Registered <br />Professional Engineer and a Professional Land Surveyor in the State of <br />Colorado, to monitor the contractors. UMC has contracted clearing and <br />grubbing, topsoil removal and storage, impoundment excavation and <br />embankment construction. UMC will contract GDL & GCL liner installation, leak <br />detection installation, sump construction, and impoundment liner installation to <br />complete the TSF project. UMC crews will place historic tails in the TSF, <br />construct and place ballast tubes on the impoundment sides, install tailings slurry <br />pipes to the impoundment, and install the decant water pumping station." <br />Section 4.3.8 QA /QC, Sub Base Construction, and Geosynthetic Clay Liner <br />Installation <br />• Change subheading to "Sub Base Construction, GDL and GCL" <br />• Insert new bullet No 2. <br />"The sub base will be constructed during a period of low flow to ensure <br />that the GDL will protect the GCL from premature hydration." <br />• Insert new bullet No 3. <br />"Liner contractor will install and test the geocomposite drainage layer in <br />accordance with manufacturer's recommendations. Installation of the <br />