TECHNICAL SPECIFICATIONS <br />SECTION 01400.2 <br />GEOSYNTHETICS CONSTRUCTION QUALITY ASSURANCE (CQA) PLAN <br />PART 1 - INTRODUCTION <br />This plan addresses the Construction Quality Assurance (CQA) procedures for the installation of the geosynthetic <br />components used for the construction of the PSES Pipe Rack Liner Extension at the Cresson Project, Teller County, <br />Colorado. This program has been developed to assure that the construction of the geosynthetic components are in <br />compliance with the project SPECIFICATIONS and to demonstrate that the regulatory requirements for the <br />construction are achieved. <br />The objective of this plan is to assure that proper materials, construction techniques, and procedures are followed by <br />the CONTRACTOR and that the intent of the design is met. This program also intends to identify problems that <br />may occur during construction and provide the means for resolution of these problems. <br />This program addresses quality assurance, not quality control. This CQA Plan is independent of the quality control <br />(QC) programs conducted by the MANUFACTURERS, INSTALLERS, and CONTRACTORS. The intent of the <br />CQA Plan is to provide independent third party verification and testing, to demonstrate that the INSTALLER and <br />CONTRACTORS have met their obligations in the supply and installation of geosynthetic materials according to <br />the design, project SPECIFICATIONS, contractual and regulatory requirements. Quality control is provided by the <br />MANUFACTURERS, INSTALLERS, and CONTRACTORS and refers to those actions taken by them to ensure <br />that their materials and workmanship meet the requirements of the plans and project SPECIFICATIONS. <br />PART 2- EXECUTION <br />2.1 DESCRIPTION OF PARTIES TO CONSTRUCTION QUALITY ASSURANCE <br />The following section provides descriptions of the parties to this CQA plan including their responsibilities and <br />qualifications. <br />A. CC &V <br />In this CQA Plan CC &V refers specifically to Cripple Creek & Victor Gold Mining Company. <br />1-111MUTEWFITeh1S <br />In this CQA Plan the MANAGER refers specifically to the individual appointed by the Cripple <br />Creek & Victor Gold Mining Company. The MANAGER is the official representative of CC &V <br />responsible for all construction activities including oversight and direction during construction. <br />The MANAGER is also responsible for coordinating construction and CQA activities for the <br />project. <br />2. The MANAGER shall serve as communications coordinator for the project initiating <br />preconstruction and resolution meetings. As communications coordinator, the MANAGER shall <br />serve as a liaison between all parties involved in the project to ensure that ongoing <br />communications are maintained. The MANAGER and CERTIFYING ENGINEER shall also <br />be responsible for the resolution of all CQA issues that arise during the installation of the <br />geosynthetics. Duties for this position include the following: <br />a. Review and approval of design DRAWINGS and project SPECIFICATIONS for all <br />geosynthetic components of the Pipe Rack Liner Extension. <br />b. Preconstruction coordination with the CQA MONITOR to ensure that the CQA <br />MONITOR has performed similar reviews of the design DRAWINGS and project <br />SPECIFICATIONS to ensure that the CQA Plan can be implemented. <br />Geosynthetics Construction Quality Assurance (CQA) Plan August 28, 2013 <br />01400.2 -1 Revision 0 <br />S \Projects \1550 - CC &V Feld Spt CQA PSES Bldg \8 0 Project Engineering and Design \8 2 SpecificahonsTSES Pipe Rack Liner Extension Specifications \01400 2 Geosynthetics CQA docx <br />