<br />Table 5. EstilIla.ted Construction Costs - Plan 4
<br />
<br /> Unit Quantity $/Unit Total Cost
<br />PUMPING PLANT NO. 4
<br />Hotors and pumps Ls Ls Ls $100,000
<br />Building Ls Ls Ls 140,000
<br />Piping and valves La Ls Ls 90,000
<br />Surge equipment Ls Ls Ls 40,000
<br />Electrical controls La Ls La 40,000
<br />Miscellaneous plant equipment Ls Ls La 20,000
<br />Subtotal $430,000
<br />Contingencies - 25% :: 70,000
<br />Field Cost $500,000
<br />Transmission Line
<br />Additional. to Plan 3 - FieJ.d Cost 50,000
<br />Pipeline
<br />(32,000 feet of 60" preten.
<br />concrete. Q = 125 cubic feet
<br />per second)
<br />Excavate trench cy 100,000 0.40 40,000
<br />Compacting b~ckfill cy 22,000 2.50 55,000
<br />Backfill cy 35,000 0.35 12,250
<br />Highw~ crossings ea. 6 1,000.00 6,000
<br />Outlet structure ea. 1 2,500.00 2,500
<br />Right-of-way easement Acres 50 200.00 10,000
<br />Furnish and lay 25Q' head pipe If' 5,000 40.00 200,000
<br />Furnish and lay 200 I head pipe If 5,000 38.00 190,000
<br />Furnish and lay 1]50 I head pipe If 22,000 36.00 792,000
<br />Pipe fittings, valves, misc. Ls La Ls 50,000
<br />Subtotal 1,351,750
<br />Contingencies - 25% ~ 342,250
<br />Field Cost 1,700,000
<br />Total fieJ.d cost 2,250,000
<br />Indirect costs - 25% + 550,000
<br /> 2,ClOO,000
<br />Additional. investigations 25,000
<br />Cost of adding to Plan 3 for Plan 4 2, Cl25, 000
<br />Construction cost - Plan 3 5,525,000
<br />Construction cost - Plan 4 $Cl,350,000
<br />
<br />r ~ ,""' ~ .", ')
<br />\J .... ,,, ..lI. ....J '-
<br />
<br />10