Laserfiche WebLink
<br />000028 <br /> <br />mission line from Fort Peck to Garrison Dam (Spec. 1411) was awarded <br />on December 6, 1946 and the contractor acknowledged notice to proceed <br />on January 30, 1947. At the start of fiscal year 1948, five months <br />later, the contract was less than one percent completed. At the close <br />of fiscal year, it was only 11 percent complete, but poles and mate- <br />rialo were becoming available in sufficient quantities that completion <br />of the contract is expected by the end of the calendar year. <br /> <br />Two transmission lines, Brush to Sterling and Sterling to Holyoke, <br />were completed in June 1948. <br /> <br />The map on the opposite page shows existing Bureau of Reclamation <br />transmission lines and also those included in the fiscal year 1948 <br />program. Also shown are the approximate locations of all REA Coopera- <br />tives to which the Bureau of Reclamation is now supplying power. <br /> <br />45 <br />