Laserfiche WebLink
<br />" <br /> <br />Powerp1ant Limitations <br /> <br />The BuRec has awarded a contract to Westinghouse Corporation to uprate the <br />eight units at Glen Canyon Dam to 167 MW each. With this contract in force <br />and actual work to begin during late 1983, it was assumed that the BuRec <br />plans to uprate other generatin9 units at Flaming Gorge, Blue Mesa, and <br />Morrow Point would be finalized and the uprated units in place before 1990. <br />The actual schedule has slipped about one year from the uprating schedule <br />used in the model and shown in the following table. This one-year slippage <br />does not impact the results during the post-1989 marketing period. <br /> <br />, <br /> <br />, <br /> <br />3 <br />