Laserfiche WebLink
<br />~,! <br />I <br /> <br />'. <br /> <br />Eagle Mountain <br />Much of the construction at Eagle Mountain was subcontracted, <br />including excavation, aggregate production, plate steel pipe, struc- <br />tural and reinforcement steel, roofing, and painting. The contrac- <br />tor placed all concrete and backfill and performed such other work <br />as could not readily be subcontracted. <br />On April 8, 1936 the contractor started the erection of a camp <br />to house his employees, a short distance south of the plant and <br />west of the District road into Division 3 camp, On April 20th <br />stripping of the reservoir area was begun and on May 2nd drilling <br />was started, preparatory to excavation in the inlet channels and <br />pump house foundation. In July excavation was extended to the <br />surge chamber and gate house site at the top of the lift, to the de- <br />livery pipe slopes, and to the sand trap. By October trimming to <br />final grade of the pump house foundation rock was under way on <br />the west side, but under the control house and a portion of the <br />main plant the material was so broken that deep excavation <br />was required, it being found necessaq at one point to carry the <br />excavation to a depth of 40 feet below the original grade. A <br />good bedrock base was finally secured and the first concrete was <br />placed in the pump house foundation walls and slabs early in <br />January 1937. <br />In the meantime rough excavation for the sand trap was com- <br />pleted and concrete placing had been started for the surge cham- <br />ber and gate house. In March the subcontractor set the first sec- <br />tions of the intake manifold and the installation was completed <br />and tested in May. Concrete work in the various structures was <br />continuous through the summer months, that in the sand trap <br />being finished June 24th, and the pump house up to the motor floor <br />in August. With the pump house up to this level it was possible <br />for the subcontractor, Consolidated Steel Corporation, Ltd., to be- <br />gin erection of the structural steel frame and crane, and this work <br />was completed in October 1937. <br />Concreting of the superstructure followed to completion in .J an- <br />uary 1938, concrete in the switch house and water tanks being fully <br />placed shortly after. The subcontractor on the delivery pipes, <br />Western Pipe and Steel Company, set up rigging and began con- <br />struction of the pipes in December 1937, finishing the job ready <br />for test two months later. In March 1938 the rolling of the oil- <br />mix reservoir lining was completed; backfill around buildings and <br />in the yard was brought up to grade; and general cleanup was in <br /> <br />" .of (- 0 <br />J..'ivu <br /> <br />PUMPING PLANTS <br /> <br />;. 2.39 <br /> <br />~ <br /> <br />I <br />