<br />Chamle Order No. 5 and No.6- Preble's Habitat
<br />
<br />The cest previded by the Centracter in Change Order Ne, 3 fer the censtructien .of the
<br />meuse habitat indicated a cest .of $4,01 per cubic yard te place 26,000 cubic yards fer a tetal cest .of
<br />$104,173, It was understeed that the Centracter's price per cubic yard was based en using en-site
<br />material, but net dredge material. If the Centracter weuld cheose te use dredge material te
<br />censtruct the meuse habitat area, the $104,173 weuld be credited back the Tewn .of Menument and
<br />the Centractor weuld be paid based en the unit price fer dredging, less a credit fer disposing the
<br />dredging material en-site, The Centracter elected te censtruct the habitat area with dredged
<br />material,
<br />
<br />Reduction in cost = $104,173 + $13,132,50 (credit) = ($117,305,50)
<br />
<br />Per the terms .of the Army Cerps .of Engineer's Individual 404 Permit and Bielegical
<br />Assessment the Tewn .of Menument was required te construct a pertien .of the new 25-feet wide
<br />meuse habitat cerrider just nerth .of the seuthern line .of Zone 4b, prier te May 15, 2002, Given
<br />time restrictiens impesed, the Tewn .of Menument elected to have the work perfermed by the
<br />Centracter te ensure that it was cempleted en time,
<br />
<br />Additional cost = $3,108,24
<br />
<br />The fellewing is a summary .of all additienal cest incurred by the Tewn .of Menument and
<br />its Centracter:
<br />
<br /> Original Cest Actual Cest Variance
<br /> Estimate Incurred
<br />* Spillway Rehabilitatien $815,640
<br />* Chimney/Blanket Drain $1,077,900
<br />* Upstream Gate $262,080
<br />* Dredging $450,000
<br />* Berrew Material $20,000
<br />Tetals: $2,625,620 ASI -$2,775,060 $149,440
<br />* Change Order Ne, 1 $0 $46,732 $46,732
<br />* Change Order Ne, 2 and 3 $0 $317,409 $317,409
<br />* Change Order Ne, 4 $0 $147,500 $147,500
<br />* Change Order Ne, 5 and 6 $0 ($114,198) ($114,198)
<br />* Design/Censt. Engineering $450,000 $692,460 $242,460
<br />* Envirenmental Engineering $0 $71,498 $71,498
<br />* Land Acquisitien $0 $167,245 $167,245
<br />* Centract Centigency $0 $61,299 $61,299
<br />* Prebbles Habitat $0 $153,750 $153,750
<br />(Costs not included in Change Orders 3-6}
<br />* Feasibility Report $5,000 $5,000 $0
<br />Tetals: $3,080,620 $4,323,755 $1,243,135