Laserfiche WebLink
<br />- 2- <br /> <br />. April 2nd - presentation and discussion of the draft final report by A W A; <br />. April 9th - receive the technical review comments from the CWCB Technical <br />Review Panel (TRP); <br />. April II th - A W A addresses the review comments from the Committee and TRP; <br />. April 14th - A W A submits the second draft final report to the CWCB, non-federal <br />sponsors, Corps of Engineers, NWS and the Committee; <br />. May 16th - CWCB receives review comments from Corps and NWS; and <br />. May 30th - A W A publishes the final report and schedules the final project meeting <br />(If requested), <br /> <br />I would like to personally thank all involved in this project for their valuable insight and support <br />over the last two years. I remain committed to helping resolve issues surrounding Cherry Creek Dam <br />and Reservoir and am available to assist in future studies. <br /> <br />Flood Protection. Water Project Plarming and Financing. Stream and Lake Protection <br />Water Supply Protection. Conservation Planning <br />