Laserfiche WebLink
<br />e ALTERNATIVE 3 -COMBINATION OF FLOOD STORAGE AND DIVERSION <br /> <br />Because diversion of the peak flow out of the watershed and complete storage of the <br />100-year flow were not feasible, a combination of storage and reconstruction of a new <br />channel is required for this alternative to be successful. Development of as much storage as <br />possible was considered as a first option to reduce the size of the channel that would be <br />required through the Lower Basin to accommodate residual flows. This flood control <br />option seemed to be the most realistic based on water rights, impacts to the Poudre River <br />and construction cost. Conceptually, a 500-cfs channel through or around the Lower Basin <br />seemed realistic to design and construct. Suitable storage locations in the Middle Basin <br />provide storage to limit residual flow to 500-cfs at the L- W Canal. This alternative <br />requires the use of a SCADA system for remote control of the hydraulic gate operations. <br />The SCADA system would include sensors to determine flooding in Dry Creek and then <br />ensure adequate capacity in the L-W Canal by opening gages into the East Vine Diversion <br />and closing the gates at the L- W Canal's diversion at the Poudre River. It also requires <br />construction of the East Vine Diversion. <br /> <br />ALTERNATIVE 3 COMPONENTS & OPTIONS <br /> <br />e <br /> <br />A combination of flood storage and diversion of the residual flows was identified in the <br />initial work as the only feasible alternative for Dry Creek flood control. In summary, the <br />plan would consist of a number of detention storage sites in the middle basin, diversion to <br />L-W Canal, and the outfall channel (East Vine Diversion) downstream of the L-W Canal. <br />Additional studies identified a number of storage and detention options that achieve the <br />objective of limiting flood flow into the L-W Canal. Each option was built around a <br />number of common features, some existing, some new features, and a number of separate <br />features specific to that option. Eventually, four distinct options were defined. They were <br />designated as Option A, B, C, and D. <br /> <br />The common design elements amongst these storage and diversion options are described <br />below. In conjunction with the common elements each option uses combinations of <br />increased capacity in existing facilities and new detention storage at different locations to <br />reduce flood flow to 500-cfs at the L-W Canal. Following the common features are <br />descriptions of each option's unique features. Costs for each alternative option discussed in <br />this portion of the report, are presented in Appendix F. <br /> <br />. <br /> <br />The largest and the first detention storage site at the start of the middle basin, a key <br />component for all options, is created in Douglas Reservoir with the use of a spillway <br />enhancement concept. With this concept the hydrologic analysis showed that Douglas <br />Reservoir could be modified to provide control for floodwater originating from the Upper <br />Basin. However, even with installation of the recommended Spillway Enhancement <br />Regulating Weir (fuse plug), the middle basin still produces a peak discharge of <br />approximately 4,000-cfs. Further analysis determined that sufficient storage could be <br />constructed to accommodate the remaining middle basin discharge volume if it was built at <br />several locations. Existing and new structures were considered when evaluating potential <br />locations for this additional storage. These potential detention locations are shown on <br />Figure 6. <br /> <br />16 <br />