<br />Johnstown. Town of - Raw Water Pipeline
<br />
<br />Authorization: SB 94-29
<br />Water Source: Big Thompson River
<br />Terms of Loan: $2,500,000 @ 4% for 30 years
<br />
<br />County: Larimer/Weld - W of Johnstown
<br />Project Yield: 2,200 ac,ft,
<br />Project Type: Pipeline Construction
<br />
<br />e
<br />
<br />The project includes the replacement of 11 miles of open ditch with a 14-16 inch pipeline
<br />from Lonetree Reservoir to the Town of Johnstown's water treatment plant including a booster
<br />station at the reservoir and connection facilities at the treatment plant. PRC Environmental
<br />Management, Inc, of Denver designed the project, The construction contract was awarded to Hall-
<br />Irwin Construction Co, of Greeley and B,T, Construction, Inc, of Broomfield August 6, 1996,
<br />Construction commenced in early October 1996 and was completed in June 1997, Project
<br />docnmentation and fina1 accounting is currently underway with substantial completion scheduled in
<br />November 1998,
<br />
<br />Durkee Ditch Companv - Rehabilitation of the Durkee Ditch
<br />
<br />Authorization: SB 97-008
<br />Water Source: Currant Creek
<br />Terms of Loan: $120,000 @ 3,75% for 30 yrs
<br />
<br />County: Delta - E of Orchard City
<br />Project Yield: 2,000 ac,ft,
<br />Project Type: Headgate and Pipeline
<br />
<br />e
<br />
<br />This $343,000 project is the construction of a new concrete headgate and turnouts, and
<br />construction of approximately 13,000 feet ofPVC pipeline replacing an open channel ditch in Delta
<br />County northeast of Delta, Colorado, The Delta and Grand Junction Office of the Natural Resource
<br />Conservation Service prepared project design, Project construction commenced September 8, 1997
<br />by K C Equipment and Consulting of Delta, Colorado, Phase I of the project was completed in
<br />December 1997, The fina1 Phase II project commenced November 2, 1998 and is scheduled for
<br />completion in December 1998,
<br />
<br />Excelsior Irril!atinl! Companv - Excelsior Ditch Rehabilitation
<br />
<br />Authorization: SB 97-008
<br />Water Source: Arkansas River
<br />Terms of Loan: $230,000 @3,75% for 30 yrs
<br />
<br />County: Pueblo - E of Pueblo
<br />Project Yield: 4,250 ac,ft,
<br />Project Type: Ditch RehablRecharge Ponds
<br />
<br />This $335,000 project is the re-construction of approximately 2 miles of open ditch, which
<br />has previously been abandoned and farmed over. Also included in the project is the construction of
<br />several pump stations for water delivery, The project is located in Pueblo County 10 miles east of
<br />Pueblo, Project design was prepared by the Pueblo Office of the Natural Resource Conservation A
<br />Service, Ralph Adkins, P,E, of Pueblo, Irrigation Engineering of AIamosa and Hendrooke ...
<br />Sprink1ers of Ft. Collins, Project construction commenced in May 1998 with project completion
<br />scheduled for December 1998,