Estimated Design and Construction Schedule <br /> Paradox Valley Pilot Evaporation Pond <br /> Optimum Time Schedule 2011 2012 2013 <br /> Months J J AS ONDJ F MA MJ J AS ONDJ F MA MJ J A <br /> Phase U U U E C O E A E A P A U U U E C O E A E A P A U U U <br /> Needed PTVCNRRRY NL GPTV NBRRY NL G <br /> Environmental Assessment 3 <br /> Design 4 <br /> Review/Finalize Design 0.5 iimi .16. <br /> Contracts 3 <br /> Construction Permitting 1 <br /> Construction 3 <br /> Estimated TOTAL(Months): 14.5 Completed by September 2012 <br /> Extended Time Schedule 2011 2012 2013 <br /> Months J J A S O N D J F MA MJ J A S O N D J F MA MJ J A <br /> Phase U U U E C O E A E A P A U U U E C O E A E A P A U U U <br /> ' Needed C N B R R Y fI L G P T V,C N B R R Y N y G{ <br /> Environmental Assessment 6 <br /> Design 6 <br /> Review/Finalize Design 1 <br /> Contracts 4 <br /> Construction Permitting 1 I <br /> Construction 4 (winter) <br /> Estimated TOTAL(Months): 22 Completed by August 2013 <br />