Item Description Estimated Contingency Estimated Total <br /> No. Construction Engineering <br /> 1 Branch Ditch Diversion $ 225,000 $ 45.000 $ 35,000 $ 305,000 <br /> 2 River Gate Replacement $ 630,000 $ 126,000 $ 95,000 $ 851,000 <br /> 3 Trash Rack Cleaning System $ 795,000 $ 159.000 $ 120,000 $ 1,074,000 <br /> TOTAL $ 1,650,000 $ 330,000 $ 250,000 $ 2,230,000 <br /> IMPLEMENTATION SCHEDULE <br /> D&A is expected to complete the design with technical back-up for submittal to CWCB by <br /> September 2014. Once approval to proceed is obtained by the CWCB,construction will begin as <br /> soon as the canal is taken out of service beginning in November of 2014 and should be completed <br /> by March 15, 2015. <br /> PERMITTING <br /> All easements and rights-of-way have been arranged for. The Company is exempt from 404 <br /> permitting as confirmed by the Army Corps of Engineers. As requested by the Army Corps of <br /> Engineer, D&A will provided written notice of the project start date. An Adams County floodplain <br /> development permit will also be needed for this project. <br /> INSTITUTIONAL CONSIDERATIONS <br /> Entities that are, or may be, involved in the design,construction, and financing of the project <br /> include: <br /> • Fulton Irrigation Ditch Company; financing and project management <br /> • Colorado Water Conservation Board (CWCB); financing and construction <br /> • Deere&Ault Consultants, Inc., design and construction <br /> The Fulton Irrigation Ditch Company will be the lead for the financing, design and construction of <br /> the project and will be the entity entering into contracts and agreements with the various entities for <br /> the service provided by each. <br /> FINANCIAL ANALYSIS AND CREDIT WORTHINESS <br /> The Fulton is applying for a loan from the CWCB in maximum amount of$1,898,500.00. The <br /> actual or estimated amounts by entity are given below: <br /> -5- <br />