Laserfiche WebLink
SECTIONFIVE Selection of Alternative and Financial Plan <br /> 5-1 <br />5. Section 5 FIVE Selection of Alternative and Financial Plan <br />5.1 ALTERNATIVE SELECTION <br />The spillway rehabilitation and internal seepage collection system was selected as the <br />preferred alternative for the Project. The preferred alternative were selected based on <br />constructability, costs, reliability, reduced impact to the environment, and provision for the <br />continued use of the asset (historic water yield). <br />5.2 LAND AND RIGHT-OF-WAY REQUIREMENTS <br />The construction of the Project will be performed on the lands owned by the SMRC. <br />5.3 PROJECT IMPLEMENTATION SCHEDULE <br />The Project will be constructed during May through December 2014. Table 5.1 is the <br />schedule for implementing this Project. <br />Table 5.1: Project Implementation Schedule <br />Date Action <br />August 2013 Submit CWCB Application and Feasibility Report <br />September 2013 CWCB Board Meeting <br />April 2014 Advertise and Bid <br />May 2014 Begin Construction <br />November 2014 Complete Construction <br />December 2014 Project Close Out <br /> <br />5.4 COST ESTIMATE <br />Appendix D presents an estimate of the construction and construction engineering costs <br />associated with the selected alternatives. Table 5.2 summarizes the costs estimated for this <br />Project. <br />