Animas -La Plata Project <br />Feb 13, 2013 Draft Transfer Inspection Report <br />12. Piping and Valves for Draining Discharge Lines <br />A 16" diameter drain pipe is connected to the 72" diameter steel pipe section of the <br />Durango Discharge Manifold (or RBIC) and to the 24" diameter steel pipe section of the City <br />of Durango Discharge Manifold (this connection is in the City of Durango valve pit). <br />The designations for these valves are: <br />• Suction manifold Isolation, 16" manually- operated butterfly valve (D1) <br />• Sump drain, 6" manually- operated butterfly valve (D2) <br />• Durango manifold discharge Isolation, 16" manually- operated butterfly valve (D3) <br />• City of Durango discharge Isolation, 16" manually- operated butterfly valve (D4) <br />• Drain discharge valve, 16" motor - operated butterfly valve (MPG) <br />TRANSFER ISSUE I STIPULATION <br />Butterfly valves condition I See Section 4 above. <br />13. Durango Discharge Manifold and Discharge Line <br />Downstream of the pumps, the individual pump discharge lines connect into the single 72" <br />diameter steel discharge manifold. This 72" diameter steel pipe extends from the pumping <br />plant structure, through an insulating flanged joint, under and past the 39' diameter air <br />chamber where it connects to the 72" diameter discharge line pipe at another insulating <br />flanged joint at station 24 +00. The Durango Pumping Plant Discharge Line starts at the end <br />of the manifold and continues through the flow measurement structure, under South Creek <br />and ends at station 43 +00. The Durango Discharge Line has one air valve at sta. 35 +23. <br />Ridges Basin Inlet Conduit (RBIC) starts at the end of this line. <br />14. Durango Discharge Line Air Chamber <br />A partially buried 39' diameter spherical air chamber and air compressor are located <br />approximately 50 feet south of the pumping plant. The air chamber has been enclosed <br />within a reinforced concrete structure with a pre- manufactured metal dome roof. <br />The air chamber is provided with a level indicating and switch module assembly. The <br />operation of the air chamber and air compressor is controlled by switch modules located at <br />predetermined water levels: <br />• Air Release <br />• Compressor ON <br />• Compressor OFF <br />• Emergency pumps OFF <br />A sealed corrosion - resistant submersible, float controlled, sump pumping unit rated at 40 <br />gal /min at 35 -feet of head with a 1/2 horsepower electric 120 Vac motor is installed in the <br />sump recess of the plant air chamber <br />Transferred Works Inspection 21 Animas -La Plata Project <br />