Laserfiche WebLink
In the 3`d Quarter of 2010 Prime Machine Inc. has iinished construction of the <br />valves and they are being painted. There is a tentative inspection date of Sept. 21-22 in <br />SLC. This district will send someone as will the Bureau of Reclamation. Prime Machine <br />Inc. has set a scheduled date of Oct. 4, 2010 to begin installation work at the Platoro site. <br />4TH Quarter-Prime Machine did begin installation work in Platoro on Oct. 5, <br />2010. They completed the work without safety or health problems. The workmanship and <br />crew were professional and accommodating. The installation crew left the Platoro site on <br />the 23`d of Oct. The Conejos Water Conservancy District has been billed for the <br />completed construction and installation of the new valves. Enclosed are pictures of the <br />completed project. <br />BY: /l� so�.--� <br />Title: m,o,�,a�s�2 <br />Date: T��o/o <br />