SCHEDULE FOR COMPLETING TASKS <br />Monitor Protocol Review and Finalization <br />Schedule appears to be manageable <br />Monitorine Protocol Implementation <br />Schedule looks fine except for the proposed dates for the Year 2 and 3 monitoring plan & budget <br />development dates. I think September - October 2009, 2010 are more realistic dates. This would give <br />me a chance to get into the data reduction/analysis and lab analysis and provide a better idea for <br />associated time and cost requirements specific to this monitoring effort. <br />Reporting <br />Based on my experience, I think the October (2009, 2010, and 2011) draft reporting dates are too early, <br />particularly with the number of sediment samples to be dry sieved. I think an end of November - early <br />December target is a more realistic goal for the draft with the final being delivered to the ED Office in <br />January. <br />PRRIP - Geomorphic Monitoring 17 of 20 Blue Mountain Consultants