Laserfiche WebLink
During excavation of the borrow material at the project site, the Contractor encountered <br />significant subsoil moisture. This required the placement of geogrid material along the haul <br />road to stabilize the road surface, which significantly improved the productivity of the haul <br />trucks. This resulted in an added cost to the project of $13,788. In order to prevent long term <br />erosion problems at the outlet, the Company elected to extend the outlet pipe to provide a better <br />downstream flow alignment. This resulted in an added cost to the project of $3,200. <br />Remobilization <br />The delay in receiving SEO approval and the subsequent loss of five critical working weeks on <br />the Mesa created a situation that the Company, Contractor, and Engineer did not want to have to <br />address. Given the high moisture content of the borrow material, it became imperative for the <br />Contractor to have long warm days to assist in drying the material. The late start date resulted in <br />shorter days, cooler nights, and less ability for the Contractor to work the material to achieve the <br />desired moisture content and density. In October 2008, it became obvious to the Company, <br />Contractor, SEO, and CWCB staff that the project could not be completed, and a winter <br />shutdown plan was submitted to SEO. <br />In the fall of 2008, the Company negotiated a new contract with the Contractor to complete the <br />project. It was based on time and productivity lost due to the delay in plan approval, the need to <br />do extensive unplanned work on the relining of the reservoir outlet (pursuant to a SEO approved <br />change order) and the need and commitment of both the Company and Contractor to finish the <br />project. Given those factors the Company negotiated a new contract to complete the project for <br />a revised contract price of $850,000 or an increase of $100,000. <br />Table 1 below is a comparison of the original construction cost presented in September 2004, the <br />revised cost estimated presented at the January 2007 Board Meeting, and the actual project <br />costs. <br />Table 1 <br />Original Est. Revised Est. Actual Costs <br />Construction Items Res.1,2 & 4 Enlarge Res. 4 Enlarge Res. 4 <br />Se t.2004 Jan.2007 Se t.2009 <br />l. Plannin n.lPermits/Water Ri hts $183,000 $157,000 $432,000 <br />2. Construction $477,100 $984,000 $990,000 <br />3. Mobilization $0 $0 $125,000 <br />4. Submittals $0 $0 $2,000 <br />5. Filter Drain/Cutoff/Drain Mat'1. $0 $0 $108,000 <br />6. Ri Ra $0 $0 $137,000 <br />7. Dam Embanlanent $0 $0 $410,000 <br />8. Tce Drain $0 $0 $10,000 <br />9. Outlet Work $0 $0 $103,000 <br />10. S illwa $0 $0 $90,000 <br />11. Instrumentation/Reve . $ $0 $5,000 <br />12. Contin enc $0 $137,000 $20,000 <br />13. Construction Mana ement $0 $55,000 160,000 <br />Totals: $660,000 $1,333,000 $1,602,000 <br />*The total,presented in column three for construction is the summation of items 3 through 11. <br />4 <br />