<br />Appendix H
<br />
<br />TOWN OF KREMMLlNGIGRR * SUPPLEMENTAL WATER SUPPLY * ESTIMATE OF
<br />PROBABLE PROJECT COST
<br />
<br /> Installed Installed Cumulative
<br /> Unit Item
<br />Item Quantity Unit Cost Cost Total
<br />Item 1-Mobilization & General
<br />Requirements
<br />Mobilization @ 8% of Subtotal of 1 LS $89,824 $89,824 $89,824
<br />Construction Costs
<br />Item 2-ILow-Lift" Pump Station
<br />Access Road 7,000 LF $2.50 $17,500
<br />Improvements at Colorado River, 1 LS $75,000. $75,000
<br />includina Bank Stabilization 00
<br />Self-Cleaning Screen, Pump System and 1 LS $10,000. $10,000
<br />Pump Pioina 00
<br />Piping to Wetwell 1 LS $10,000. $10,000
<br /> 00
<br />Slide Gate 1 EA $3,000 $3,000
<br />Concrete Wetwell 1 LS $30,000 $30,000
<br />Submersible Pumps wI Check Valves 3 EA $20,000 $60,000
<br />and Slide Rail Svstem
<br />Aluminum Checker Plate for Pump 3 EA $1,000 $3,000
<br />Access
<br />Wetwell Access Manhole and Steps 1 LS $1,000 $1,000
<br />6" Gate Valves 3 EA $1,500 $4,500
<br />6" Flanaed DIP Piping and FiUinas 1 LS $10,000 $10,000
<br />Controls, MCC's, Electrical and Lightning 1 LS $30,000 $30,000
<br />Protection
<br /> Total $254,000 $343,824
<br />Item 3-12" HOPE Low Lift Forcemain
<br />HDPE Forcemain 5,750 LF $41.09 $236,268
<br />Culvert Sleeves 1 EA. $10,000 $10,000
<br />ARV's 1 EA. $5,000 $5,000
<br />EnerQV Dissipators 1 EA. $1,000 $1,000
<br />14" Gate Valves 2 EA $2,000 $4,000
<br /> Total $256,268 $600,091
<br />Item 4-IHi-Lift" Station
<br />Concrete Wetwell 1 LS $70,000 $70,000
<br />Excavation and Backfill 1 LS $10,000 $10,000
<br />Architectural Buildina Treatments 1 LS $40,000 $40,000
<br />Vertical Turbine Pumps 3 EA $20,000 $60,000
<br />Soft Start Drive 3 EA $6,000 $18,000
<br />Pump Control Valves 3 EA $7,500 $22,500
<br />6" Knife Gate Valves 3 EA $1,500 $4,500
<br />6" Flanaed DIP Pipina and Fittinas 1 LS $15,000 $15,000
<br />
<br />11