Discharge.--
<br />PLATTE RIVER BASIN
<br />SOUTH PLATTE RIVER BELOW CHATFIELD RESERVOIR
<br />Location.--
<br />Drainage and Period of Record.--
<br />Lat. 39°33'45",Long. 105°03'35", SE¼, sec. 1, T.6 S., R.69 W., Jefferson County, Hydrologic Unit 10190002.
<br />3,018 mi². 1985 to present.
<br />Graphic water stage recorder and satellite monitoring DCP with shaft encoder installed in a formed concrete well and
<br />shelter. An electric drop tape is used for referencing. There is no outside reference. A cableway is located at the gage.
<br />Satellite equipment is owned and maintained by CO DWR.
<br />Equipment.--
<br />Hydrologic Conditions.--
<br />Gage-Height Record.--
<br />Datum Corrections.--
<br />Rating.--
<br />Discharge.--
<br />Special Computations.--
<br />Remarks.--
<br />Recommendations.--
<br />Native flow is regulated by Chatfield Reservoir, as well as by many reservoirs further upstream. Releases from Chatfield
<br />during flood events are regulated to limit the total flow at the Henderson gage (downstream from Denver) to 5000 cfs.
<br />There are no minimum streamflow requirements for Chatfield releases. On many days the reservoir outlets are completely
<br />closed and flow at the gage consists of small amounts of seepage or gate leakage.
<br />The primary record is hourly averages of 15 minute satellite data with chart back up. Daily max and min values agreed with
<br />the corrected chart values to within +-0.02 foot. No encoder data corrections were applied. Record for March 23 and 24
<br />were taken from the chart. The record is complete and reliable.
<br />Levels were run on Sept. 23, 2009 using RM No. 1, and showed the new elevation of the RP to be 0.12 ft higher, at 20.09
<br />ft, which was also the case for levels run July 26, 2006. No corrections were made, as shifts are correlating close to zero.
<br />Further investigation needs to be done to determine if the 20.09 ft reference elevation needs to be updated.
<br />The control is a massive sloped concrete dam approximately 50 feet below the gage, with a deep stilling basin that is about
<br />1000 ft. long back to the reservoir outlet pipe. This is a critical head measurement structure with a perfectly stilled pool at
<br />low flows. Anchor moss may grow at low flows, but this is easily removed. Measurement conditions near the gage are not
<br />good. The channel is very rocky and flow is deep and often extremely slow. The initial and subsequent ratings have
<br />incorporated a lot of scatter in the measurements. Variations in shifts at lower (wade-able) flows are probably more due to
<br />measurement error than to conditions affecting the control. If enough measurements are made with the highest possible
<br />precision, it should be possible to develop a table that does not require shifts, or measurements at lower flows. In fact, shift
<br />variations at low flows have at times made administration of the release problematic. Shift variations have been seen for
<br />high flow, cable measurements. Possible sources for this could be partial submergence of the control and growth of pond
<br />weed in the stilling basin. The extreme low end of the rating has not been verified in a long time. The PZF was observed to
<br />be 0.27 ft when the gage pool was drained and cleaned in November, 2007. Seepage flows (usually less than 0.5 cfs) are
<br />not measureable, and the near zero portions of the rating have been extensions to PZF from measurements in the 5 cfs
<br />range. Flows below 0.5 cfs should be considered estimates. Rating No. 3 was continued in use this year and is well
<br />defined to 2500 cfs. Eighteen measurements (No. 403-420) were made this year, ranging in discharge from 27.6 to 1570
<br />cfs. These measurements contain the range in flow with exception of low flow days on Oct. 1-5, 8-12, 29-31, 2009; Nov. 1-
<br />30; Dec. 1, 2, 2009; Jan.1-8; Feb 3-8; Mar 1-4, July 14-18; Sep. 2, 3, 5-9, 13-30, 2010. Measurement 413 captured the
<br />water year high flow day of April 27. The peak flow of 1580 cfs occurred at 1115 on April 27, 2010 at a gage height of 4.65
<br />ft. with a shift of 0.03 ft. It exceeded measurement no. 413 (made the same day) by 0.01 ft in stage.
<br />Shifting control method was used all year. However, the control is a fairly massive structure and if kept clean of moss
<br />should have no source for shifting. The main source of shifts at this gage is very likely to be some degree of measurement
<br />error, combined with some degree of stage shifting. Big shifts have been seen at higher flows and are currently under
<br />investigation. This year’s measurements show unadjusted shifts ranging from -0.07 ft to 0.03 ft. Shifts were distributed by
<br />time with consideration of stage for the periods: October 1, 2009 through April 21, 2010, using Msmts 403-412, which were
<br />given full weight, except pairs 408-409 and 411-412, which were adjusted up to 3%. The pairs were training
<br />measurements made at the same time and were adjusted so that a single shift was used for each pair. And, June 1-
<br />September 30, using Msmts 414-421, with Nos. 419 and 420 being adjusted 2% to smooth distribution. Shifts were
<br />distributed by stage using two variable stage shift relationships: PLACHACO10-1 based on Msmts 412-413, both given full
<br />weight, and applied April 21-27, 2010. This table defined the year’s peak flow. And, PLACHACO10-2, based on Msmts
<br />413-414, with No. 414 adjusted 2%, and applied April 27-June 1, 2010.
<br />The record is good, except for seepage flows below 0.5 cfs which are estimated and poor. Station maintained by Jana Ash
<br />and Tony Arnett and record developed by Tony Arnett.
<br />Pro-active measures should be taken with regard to shift variations at high flow. A staff should be installed below the
<br />control to check that high flow measurements are not encountering backwater. Cableway markings should be verified
<br />using a tagline at water level and a horizontal tape strung between the A-Frames. Vegetative growth in the stilling pool
<br />should be observed. Levels should be run to confirm elevations of the RM’s and PZF, and reconcile any tape length
<br />problems. Finally, the flushing system should be operated at least once, to check the flush water supply plumbed in from
<br />the Last Chance Ditch pipeline.
<br />2010Water Year
|