Emil <br />�M_V <br />amee, <br />In addition to the structural fill placement for the PSSA toe berm embankment, the contractor continued fill <br />operations and compaction by method specification for ADR haul road, location at approximate Sta.78 +00 — 83 +00 <br />and near midway at approximate Sta. 48 +00 — 50 +00. A Cat D8 Dozer with GPS and a Cat C556 Smooth Drum <br />roller was utilized. Progress is expected to continue. <br />See Hwy 67 below for detail of embankment fill progress. <br />Note: An Amec field representative monitored structural fill material temperatures placed within the areas of fill <br />during all shifts. Average structural fill temperatures were above 32 °F <br />Clay (SLF) Processing: <br />Cameron Site: No clay mining or processing occurred during this reporting period due to a saturated site from <br />previous rains. <br />Squaw Gulch Site: <br />Clay stripping and stockpiling occurred during this reporting period. <br />Underdrain System: <br />Secondary Underdrain: No work was performed on the Secondary underdrain during this reporting period. <br />A total of 1380 feet of Secondary underdrain has been completed. <br />Primary Underdrain: No work was performed on the Primary underdrain during this reporting period. <br />A total of 1280 feet of Primary underdrain has been completed. <br />Temporary Underdrain: No work was performed on the temporary underlain during this reporting period. <br />Tree /Slash Clearing, Chipping: <br />Seed Masters paused operations until further notice. <br />S) Underground Workings <br />Exploratory excavation was performed on underground working No. U6269 and No. 6011. These sites require <br />further excavation and exploratory efforts. <br />Confirmatory drilling was performed on underground working No. 6051, No. 6147, No. 6187, No. 6239 during this <br />reporting period. All drill hole locations were established on a 4 -foot center isolating any voids found. Further <br />remediation efforts will be ongoing until remediated. Summary of the remediation efforts will follow 100% <br />remediation. <br />During this reporting period exploratory excavation was performed on UG working No. 6269 and No. 6011. Site's <br />listed require further investigation and excavation into bedrock as remediation continues to be completed. <br />Underground working No. 6051, Concrete Plug was placed and will continue with remediation efforts until <br />remediation is complete. A cemented rockfill is scheduled to be placed to complete this working. <br />Underground Working No. 6239, site is prepared for geogrid to complete remediation. <br />During this reporting period remediation efforts were performed and completed on UG working No.6137, No. 6139, <br />No. 6140, No. 6197, No. 6198 and No. 6199. Sites listed were excavated to practical refusal into rock varying <br />depths depending on the working remediated. The site for each working was then backfilled in 2 foot loose lifts to <br />approximate planned subgrade elevation using the onsite structural fill (excavated material) and "bucket tamped" <br />Page 2 of 7 MLE2 WE 08.17.13.doc <br />