My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2013-08-23_REPORT - M1980244 (4)
DRMS
>
Day Forward
>
Report
>
Minerals
>
M1980244
>
2013-08-23_REPORT - M1980244 (4)
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 5:24:09 PM
Creation date
8/27/2013 9:05:54 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1980244
IBM Index Class Name
REPORT
Doc Date
8/23/2013
Doc Name
Weekly CQA Reports- 7/06/13 and 7/13/13.
From
CC&V
To
DRMS
Email Name
TC1
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
15
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
i <br />• <br />CRIPPLE CREEK & VICTOR GOLD MINING Co. <br />Squaw Gulch (VLF), HWY 67 Realignment Field Monitoring Summary Weekly Report <br />Owner: Cripple Creek & Victor Gold Mining Co. Project Number: Date <br />Project: Squaw Gulch (VLF), Hwy 67 Realignment 74201125N0. * * * *. * * ** 07.06.2013 <br />Location: Cripple Creek & Victor Gold Mine, Colorado <br />Contractor: Ames Construction Co. Inc. <br />Reporting Period: 06.30.13 thru 07.06.13 <br />Days <br />S <br />M <br />T <br />W <br />T <br />F <br />S <br />Work Shifts <br />- <br />D <br />D <br />- <br />N <br />N <br />- <br />- <br />- <br />- <br />D = Day Shift N = Night Shift <br />W = Weather <br />Da <br />DivIS 10N l, <br />Mlly /N��yD S� �r fl ©�Y <br />Y <br />Ambient Temperature Ranges for reporting period: Weather_ conditions for reporting period: ^_ <br />Low: 43 °F — 45°F Cloud Cover: Cloudy / partly Cloudy /Clear <br />High: 75 °F — 77 °F f Precipitation: Light P.M. Showers <br />Wind: Calm to Gusts at times <br />Ames: Structural fill haul was shut down on Monday the I" at approximately 14:15hrs due to slick haul road <br />conditions caused by afternoon rains. Night shift was called off at approximately 19:45 hrs due to the wet <br />conditions as-well. <br />No work occurred on July 4'h, 5`t' and 6`h of July in observance of Holiday. Construction is expected to <br />resume on Monday July 8"'. <br />Amec: None <br />Project Issues: Haul Road design — Projects is waiting on confirmation from Mine operations to proceed with <br />design option <br />Planning: Continuing Construction activities and scheduling for VLF and HWY 67. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />I) Earthworks <br />A) VLF (Phase 1) <br />Topsoil Stripping: <br />No topsoil stripping occurred during this during this reporting period. However the contractor is expected to resume <br />during the next reporting period. <br />Structural Fill: <br />Production drilling was performed during this reporting period within the planned limits of the PSSA and in several <br />k)cations within the planned VLF Phase I limits. <br />Three production blasts's occurred during this reporting period within the planned PSSA and planned VLF Phase I <br />limit's. In addition 'cut" material was generated as structural fill using several Cat dozers in several locations within <br />the VLF Phase I limits. Material generated as structural fill was transported by Cat 777 and 740 haul trucks for the <br />HWY 67 embankment fill. <br />Page 1 of 6 MLE2 WE 07.06.13.doc <br />
The URL can be used to link to this page
Your browser does not support the video tag.