Bowie No. 2 notes for site visit July 18, 2013: <br />I arrived on site around 9 am to meet with Bill Bear and it was obvious there had <br />been a substantial rain event the previous night. Based on site observations, it looks <br />like it hit hardest in the area of the mine office. Ditches and culverts were already <br />being cleaned out upon my arrival. No significant erosion or damage to any ditches <br />or culverts, but a lot of sediment was evident in the channel bottoms. <br />Our next stop was the gob pile, which had also received a significant amount of rain. <br />This was the first big storm event after all of the ditches had been graded, and other <br />than two ditches, there was positive drainage on both gob piles. Both ditches Ditch <br />F -17 and F10 had standing water. Ditch F17 had become clogged with sediment. <br />An excavator cleaned out the sediment and had the water flowing again before I left <br />the site. Ditch F10 (old F1) may have been ponding in the high spot between old <br />ditches F1 and D8. Where the two ditches split, there was likely a flat spot.. There <br />was not a lot of standing water between the ditches, and it was scheduled to be re- <br />graded later in the afternoon. <br />Bill and I walked the site, and the gob on the surface was very wet, but traversable. <br />We walked both diversion ditches, including the new West Diversion Ditch #1 <br />extension. Some upslope had raveled down into the channel bottom, but it help up <br />very well under what was likely a very large sheet flow. This is part of the surficial <br />slumping discussed in the June 19 report that is to be expected until the upslope <br />reaches its equilibrium point. No maintenance is required at this time. Monitoring <br />will continue to occur after large rain events, and maintenance will occur as <br />necessary. West Diversion Ditch #1 looked good. <br />Ponds C was full of water, and Pond B had received a little bit of flow. Ponds D and <br />F had very little water. <br />The air permit for gob pile #3 is very close to being complete. CDPHE has approved <br />the model with mitigation in the form of fencing and signs to be placed around <br />Bowie's property. <br />There is still work to be done at gob pile #3 before gob can be hauled there. Final <br />preparation will involve salvaging additional coverfill material in the footprint of the <br />waste pile and placing it into stockpile. Coverfill for the gob pile #2 material balance <br />will also be salvaged from this location and be hauled back to the gob pile #2 and #4 <br />stockpile. A potential seep from the Fire Mountain Canal has be discovered in the <br />footprint of gob pile #3, below ditch J -9 -1. Jim will be designing an underdrain as <br />part of his certification report. <br />The monsoon season has started, so for the next few days and into next week most <br />parts of the western slope could receive precipitation. <br />