COAL REFUSE DISPOSAL AREA EXPANSION - PHASE II <br />RECLAMATION COST ESTIMATE (RN12 -06) <br />REFUSE HAULROAD AND REFUSE PILE COVER AND REVEGETATION <br />Cover and Soil Material Replacement and Revegetation <br />Cover material replacement - 121,000cy @ $0.90 /cy $108,900 <br />Soil material replacement — 72,600cy @ $0.90 /cy 65,340 <br />Revegetation — 30ac x $285.64/ac 8,570 <br />Subtotal $182,810 <br />Indirect and Administrative Costs (8 %) $14,630 <br />Project Total Cost $197,440 <br />Notes: Dimensions from Map 24 (Sheet 1 of 3) <br />All acreages, volumes, and costs reflect phased construction, and assume that at any given time the <br />maximum reclamation liability (worst case) will correspond to approximately 1/3 of the total area and 1/3 of <br />the corresponding volumes (cover material and soil) <br />Costs from Means Site Work and Landscape Cost Data <br />TR09 -67 06/19/09 <br />